[Code of Federal Regulations]
[Title 40, Volume 6]
[Revised as of July 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 40CFR60.1]

[Page 22]
 
                   TITLE 40--PROTECTION OF ENVIRONMENT
 
         CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)
 
PART 60--STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES--Table of Contents
 
                      Subpart A--General Provisions
 
Sec. 60.1  Applicability.


    (a) Except as provided in subparts B and C, the provisions of this 
part apply to the owner or operator of any stationary source which 
contains an affected facility, the construction or modification of which 
is commenced after the date of publication in this part of any standard 
(or, if earlier, the date of publication of any proposed standard) 
applicable to that facility.
    (b) Any new or revised standard of performance promulgated pursuant 
to section 111(b) of the Act shall apply to the owner or operator of any 
stationary source which contains an affected facility, the construction 
or modification of which is commenced after the date of publication in 
this part of such new or revised standard (or, if earlier, the date of 
publication of any proposed standard) applicable to that facility.
    (c) In addition to complying with the provisions of this part, the 
owner or operator of an affected facility may be required to obtain an 
operating permit issued to stationary sources by an authorized State air 
pollution control agency or by the Administrator of the U.S. 
Environmental Protection Agency (EPA) pursuant to Title V of the Clean 
Air Act (Act) as amended November 15, 1990 (42 U.S.C. 7661). For more 
information about obtaining an operating permit see part 70 of this 
chapter.
    (d) Site-specific standard for Merck & Co., Inc.'s Stonewall Plant 
in Elkton, Virginia. (1) This paragraph applies only to the 
pharmaceutical manufacturing facility, commonly referred to as the 
Stonewall Plant, located at Route 340 South, in Elkton, Virginia 
(``site'').
    (2) Except for compliance with 40 CFR 60.49b(u), the site shall have 
the option of either complying directly with the requirements of this 
part, or reducing the site-wide emissions caps in accordance with the 
procedures set forth in a permit issued pursuant to 40 CFR 52.2454. If 
the site chooses the option of reducing the site-wide emissions caps in 
accordance with the procedures set forth in such permit, the 
requirements of such permit shall apply in lieu of the otherwise 
applicable requirements of this part.
    (3) Notwithstanding the provisions of paragraph (d)(2) of this 
section, for any provisions of this part except for Subpart Kb, the 
owner/operator of the site shall comply with the applicable provisions 
of this part if the Administrator determines that compliance with the 
provisions of this part is necessary for achieving the objectives of the 
regulation and the Administrator notifies the site in accordance with 
the provisions of the permit issued pursuant to 40 CFR 52.2454.

[40 FR 53346, Nov. 17, 1975, as amended at 55 FR 51382, Dec. 13, 1990; 
59 FR 12427, Mar. 16, 1994; 62 FR 52641, Oct. 8, 1997]