PART 63--NATIONAL EMISSION STANDARDS FOR HAZARDOUS AIR POLLUTANTS FOR SOURCE CATEGORIES--Table of Contents
 
    Subpart D--Regulations Governing Compliance Extensions for Early 
                 Reductions of Hazardous Air Pollutants
 
Sec. 63.77  Application procedures.

    (a) To apply for an alternative emission limitation under 
Sec. 63.72, an owner or operator of the source shall file a permit 
application with the appropriate permitting authority.
    (b) Except as provided in paragraph (e) of this section, the permit 
application shall contain the information required by Sec. 63.74, as 
applicable, and the additional information required for a complete 
permit application as specified by the applicable permit program 
established pursuant to title V of the Act.
    (c) Permit applications under this section for sources not subject 
to enforceable commitments shall be submitted by the later of the 
following dates:
    (1) 120 days after proposal of an otherwise applicable standard 
issued under section 112(d) of the Act; or
    (2) 120 days after the date an applicable permit program is approved 
or established pursuant to title V of the Act.

[[Page 97]]

    (d) Permit applications for sources subject to enforceable 
commitments pursuant to Sec. 63.75 shall be submitted no later than 
April 30, 1994.
    (e) If the post-reduction year does not end at least one month 
before the permit application deadline under paragraph (c) of this 
section, the source may file the post-reduction emissions information 
required under Sec. 63.74(d)(2), (d)(3), and (d)(5) later as a 
supplement to the original permit application. In such cases, this 
supplemental information shall be submitted to the permitting authority 
no later than one month after the end of the post-reduction year.
    (f) If a source test will be the supporting basis for establishing 
post-reduction emissions for one or more emissions units in the early 
reductions source, the test results shall be submitted by the applicable 
deadline for submittal of a permit application as specified in paragraph 
(c) or (d) of this section.
    (g) Review and disposition of permit applications submitted under 
this section will be accomplished according to the provisions of the 
applicable permit program established pursuant to title V of the Act.

[58 FR 62543, Nov. 29, 1993, as amended at 59 FR 59924, Nov. 21, 1994]