Sec. 65.6  Startup, shutdown, and malfunction plan and procedures.

    (a) Paragraphs (b) and (c) of this section do not apply to Group 2A 
or Group 2B process vents.
    (b) Startup, shutdown, and malfunction plan. (1) Description and 
purpose of plan. The owner or operator of a regulated source shall 
develop and implement a written startup, shutdown, and malfunction plan 
that describes, in detail, procedures for operating and maintaining the 
regulated source during periods of startup, shutdown, and malfunction 
and a program of corrective action for malfunctioning process and air 
pollution control equipment used to comply with the relevant standard. 
The plan shall also address routine or otherwise predictable CPMS 
malfunctions. This plan shall be developed by the owner or operator by 
the regulated source's implementation date as specified in 
Sec. 65.1(f), or for sources referenced from 40 CFR part 63, 
subpart F, by the compliance date specified in that subpart. The 
requirement to develop and implement this plan shall be incorporated 
into the source's title V permit. This requirement is optional for 
equipment that must comply with subpart F of this part. It is not 
optional for equipment equipped with a closed vent system and control 
device subject to subpart G of this part. The purposes of the startup, 
shutdown, and malfunction plan are described in the following:
    (i) To ensure that owners or operators are prepared to correct 
malfunctions as soon as practical after their occurrence in order to 
minimize excess emissions of regulated material (excess emissions are 
defined in Sec. 65.3(a)(4)); and
    (ii) To reduce the reporting burden associated with periods of 
startup, shutdown, and malfunction (including corrective action taken to 
restore malfunctioning process and air pollution control equipment to 
its normal or usual manner of operation).
    (2) Operation of source. During periods of startup, shutdown, and 
malfunction, the owner or operator of a regulated source shall operate 
and maintain such source (including associated air pollution control 
equipment and CPMS) in accordance with the procedures specified in the 
startup, shutdown, and malfunction plan developed under paragraph (b)(1) 
of this section.
    (3) Use of additional procedures. To satisfy the requirements of 
this section to develop a startup, shutdown, and malfunction plan, the 
owner or operator may use the regulated source's standard operating 
procedures (SOP) manual, or an Occupational Safety and Health 
Administration (OSHA) or other plan, provided the alternative plans meet 
all the requirements of this section and are made available for 
inspection when requested by the Administrator.
    (4) Revisions to the plan. Based on the results of a determination 
made under Sec. 65.3(b)(3), the Administrator may require that 
an owner or operator of a regulated source make changes to the startup, 
shutdown, and malfunction plan for that source. The Administrator may 
require reasonable revisions to a startup, shutdown, and malfunction 
plan, if the Administrator finds that the plan is inadequate as 
specified in the following:
    (i) Does not address a startup, shutdown, and malfunction event of 
the

[[Page 35]]

CPMS, the air pollution control equipment, or the regulated source that 
has occurred; or
    (ii) Fails to provide for the operation of the regulated source 
(including associated air pollution control equipment and CPMS) during a 
startup, shutdown, and malfunction event in a manner consistent with 
good air pollution control practices for minimizing emissions to the 
extent practical; or
    (iii) Does not provide adequate procedures for correcting 
malfunctioning process and/or air pollution control equipment as quickly 
as practicable; or
    (iv) Does not provide adequate measures to prevent or minimize 
excess emissions to the extent practical as specified and defined in 
Sec. 65.3(a)(4).
    (5) Additional malfunction plan requirements. If the startup, 
shutdown, and malfunction plan fails to address or inadequately 
addresses an event that meets the characteristics of a malfunction but 
was not included in the startup, shutdown, and malfunction plan at the 
time the owner or operator developed the plan, the owner or operator 
shall revise the startup, shutdown, and malfunction plan within 45 days 
after the event to include detailed procedures for operating and 
maintaining the regulated source during similar malfunction events, and 
a program of corrective action for similar malfunctions of process or 
air pollution control equipment or CPMS.
    (6) Retain plan on site. The current plan must be kept on site at 
all times.
    (c) Periodic startup, shutdown, and malfunction reports. During the 
reporting period, reports shall only be required for startup, shutdown, 
and malfunction during which excess emissions as defined in 
Sec. 65.3(a)(4) occur. A startup, shutdown, and malfunction 
report can be submitted as part of a periodic report required under 
Sec. 65.5(e), or on a more frequent basis if specified 
otherwise in a relevant standard or as established otherwise by the 
permitting authority in the source's title V permit. The startup, 
shutdown, and malfunction report shall be delivered or postmarked by the 
30th day following the end of each calendar half (or other calendar 
reporting period, as appropriate), unless the information is submitted 
with the periodic report. The report shall include the following 
information, as appropriate:
    (1) The name, title, and signature of the owner or operator or other 
responsible official certifying its accuracy.
    (2) The number of startup, shutdown, malfunction events and the 
total duration of all periods of startup, shutdown, and malfunction for 
the reporting period.
    (3) If actions taken by an owner or operator during a startup, 
shutdown, and malfunction of a regulated source, or of a control device 
or monitoring system required for compliance (including actions taken to 
correct a malfunction) are consistent with the procedures specified in 
the source's startup, shutdown, and malfunction plan, then the owner or 
operator shall state such information in a startup, shutdown, and 
malfunction report.
    (4) If at any time an action taken by an owner or operator, during a 
startup, shutdown, or malfunction (including actions taken to correct a 
malfunction) during which excess emissions occur, as defined in 
Sec. 65.3(a)(4), is not consistent with the procedures 
specified in the regulated source's startup, shutdown, and malfunction 
plan, the owner or operator shall report the actions taken for that 
event as part of the periodic report. The report shall explain the 
circumstances of the event, the reasons for not following the startup, 
shutdown, and malfunction plan, and whether any excess emissions and/or 
parameter monitoring exceedances are believed to have occurred.