Sec. 70.7  Permit issuance, renewal, reopenings, and revisions.

    (a) Action on application. (1) A permit, permit modification, or 
renewal may be issued only if all of the following condition have been 
met:
    (i) The permitting authority has received a complete application for 
a permit, permit modification, or permit renewal, except that a complete 
application need not be received before issuance of a general permit 
under Sec. 70.6(d) of this part;
    (ii) Except for modifications qualifying for minor permit 
modification procedures under paragraphs (e) (2) and (3) of this 
section, the permitting authority has complied with the requirements for 
public participation under paragraph (h) of this section;

[[Page 228]]

    (iii) The permitting authority has complied with the requirements 
for notifying and responding to affected States under Sec. 
70.8(b) of this part;
    (iv) The conditions of the permit provide for compliance with all 
applicable requirements and the requirements of this part; and
    (v) The Administrator has received a copy of the proposed permit and 
any notices required under Sec.Sec. 70.8(a) and 
70.8(b) of this part, and has not objected to issuance of the permit 
under Sec. 70.8(c) of this part within the time period 
specified therein.
    (2) Except as provided under the initial transition plan provided 
for under Sec. 70.4(b)(11) of this part or under regulations 
promulgated under title IV of title V of the Act for the permitting of 
affected sources under the acid rain program, the program shall provide 
that the permitting authority take final action on each permit 
application (including a request for permit modification or renewal) 
within 18 months, or such lesser time approved by the Administrator, 
after receiving a complete application.
    (3) The program shall also contain reasonable procedures to ensure 
priority is given to taking action on applications for construction or 
modification under title I, parts C and D of the Act.
    (4) The permitting authority shall promptly provide notice to the 
applicant of whether the application is complete. Unless the permitting 
authority requests additional information or otherwise notifies the 
applicant of incompleteness within 60 days of receipt of an application, 
the application shall be deemed complete. For modifications processed 
through minor permit modification procedures, such as those in 
paragraphs (e) (2) and (3) of this section, the State program need not 
require a completeness determination.
    (5) The permitting authority shall provide a statement that sets 
forth the legal and factual basis for the draft permit conditions 
(including references to the applicable statutory or regulatory 
provisions). The permitting authority shall send this statement to EPA 
and to any other person who requests it.
    (6) The submittal of a complete application shall not affect the 
requirement that any source have a preconstruction permit under title I 
of the Act.
    (b) Requirement for a permit. Except as provided in the following 
sentence, Sec. 70.4(b)(12)(i), and paragraphs (e) (2)(v) and 
(3)(v) of this section, no part 70 source may operate after the time 
that it is required to submit a timely and complete application under an 
approved permit program, except in compliance with a permit issued under 
a part 70 program. The program shall provide that, if a part 70 source 
submits a timely and complete application for permit issuance (including 
for renewal), the source's failure to have a part 70 permit is not a 
violation of this part until the permitting authority takes final action 
on the permit application, except as noted in this section. This 
protection shall cease to apply if, subsequent to the completeness 
determination made pursuant to paragraph (a)(4) of this section, and as 
required by Sec. 70.5(a)(2) of this part, the applicant fails 
to submit by the deadline specified in writing by the permitting 
authority any additional information identified as being needed to 
process the application.
    (c) Permit renewal and expiration. (1) The program shall provide 
that:
    (i) Permits being renewed are subject to the same procedural 
requirements, including those for public participation, affected State 
and EPA review, that apply to initial permit issuance; and
    (ii) Permit expiration terminates the source's right to operate 
unless a timely and complete renewal application has been submitted 
consistent with paragraph (b) of this section and Sec. 
70.5(a)(1)(iii) of this part.
    (2) If the permitting authority fails to act in a timely way on a 
permit renewal, EPA may invoke its authority under section 505(e) of the 
Act to terminate or revoke and reissue the permit.
    (d) Administrative permit amendments. (1) An 
``administrative permit amendment'' is a 
permit revision that:
    (i) Corrects typographical errors;
    (ii) Identifies a change in the name, address, or phone number of 
any person identified in the permit, or provides a

[[Page 229]]

similar minor administrative change at the source;
    (iii) Requires more frequent monitoring or reporting by the 
permittee;
    (iv) Allows for a change in ownership or operational control of a 
source where the permitting authority determines that no other change in 
the permit is necessary, provided that a written agreement containing a 
specific date for transfer of permit responsibility, coverage, and 
liability between the current and new permittee has been submitted to 
the permitting authority;
    (v) Incorporates into the part 70 permit the requirements from 
pre[chyph]con[chyph]struc[chyph]tion review permits authorized under an 
EPA-approved program, provided that such a program meets procedural 
requirements substantially equivalent to the requirements of 
Sec.Sec. 70.7 and 70.8 of this part that would be 
applicable to the change if it were subject to review as a permit 
modification, and compliance requirements substantially equivalent to 
those contained in Sec. 70.6 of this part; or
    (vi) Incorporates any other type of change which the Administrator 
has determined as part of the approved part 70 program to be similar to 
those in paragraphs (d)(1) (i) through (iv) of this section.
    (2) Administrative permit amendments for purposes of the acid rain 
portion of the permit shall be governed by regulations promulgated under 
title IV of the Act.
    (3) Administrative permit amendment procedures. An administrative 
permit amendment may be made by the permitting authority consistent with 
the following:
    (i) The permitting authority shall take no more than 60 days from 
receipt of a request for an administrative permit amendment to take 
final action on such request, and may incorporate such changes without 
providing notice to the public or affected States provided that it 
designates any such permit revisions as having been made pursuant to 
this paragraph.
    (ii) The permitting authority shall submit a copy of the revised 
permit to the Administrator.
    (iii) The source may implement the changes addressed in the request 
for an administrative amendment immediately upon submittal of the 
request.
    (4) The permitting authority may, upon taking final action granting 
a request for an administrative permit amendment, allow coverage by the 
permit shield in Sec. 70.6(f) for administrative permit 
amendments made pursuant to paragraph (d)(1)(v) of this section which 
meet the relevant requirements of Sec.Sec. 70.6, 
70.7, and 70.8 for significant permit modifications.
    (e) Permit modification. A permit modification is any revision to a 
part 70 permit that cannot be accomplished under the program's 
provisions for administrative permit amendments under paragraph (d) of 
this section. A permit modification for purposes of the acid rain 
portion of the permit shall be governed by regulations promulgated under 
title IV of the Act.
    (1) Program description. The State shall provide adequate, 
streamlined, and reasonable procedures for expeditiously processing 
permit modifications. The State may meet this obligation by adopting the 
procedures set forth below or ones substantially equivalent. The State 
may also develop different procedures for different types of 
modifications depending on the significance and complexity of the 
requested modification, but EPA will not approve a part 70 program that 
has modification procedures that provide for less permitting authority, 
EPA, or affected State review or public participation than is provided 
for in this part.
    (2) Minor permit modification procedures - (i) 
Criteria. (A) Minor permit modification procedures may be used only for 
those permit modifications that:
    (1) Do not violate any applicable requirement;
    (2) Do not involve significant changes to existing monitoring, 
reporting, or recordkeeping requirements in the permit;
    (3) Do not require or change a case-by-case determination of an 
emission limitation or other standard, or a source-specific 
determination for temporary sources of ambient impacts, or a visibility 
or increment analysis;
    (4) Do not seek to establish or change a permit term or condition 
for which there is no corresponding underlying

[[Page 230]]

applicable requirement and that the source has assumed to avoid an 
applicable requirement to which the source would otherwise be subject. 
Such terms and conditions include:
    (A) A federally enforceable emissions cap assumed to avoid 
classification as a modification under any provision of title I; and
    (B) An alternative emissions limit approved pursuant to regulations 
promulgated under section 112(i)(5) of the Act;
    (5) Are not modifications under any provision of title I of the Act; 
and
    (6) Are not required by the State program to be processed as a 
significant modification.
    (B) Notwithstanding paragraphs (e)(2)(i)(A) and (e)(3)(i) of this 
section, minor permit modification procedures may be used for permit 
modifications involving the use of economic incentives, marketable 
permits, emissions trading, and other similar approaches, to the extent 
that such minor permit modification procedures are explicitly provided 
for in an applicable implementation plan or in applicable requirements 
promulgated by EPA.
    (ii) Application. An application requesting the use of minor permit 
modification procedures shall meet the requirements of Sec. 
70.5(c) of this part and shall include the following:
    (A) A description of the change, the emissions resulting from the 
change, and any new applicable requirements that will apply if the 
change occurs;
    (B) The source's suggested draft permit;
    (C) Certification by a responsible official, consistent with 
Sec. 70.5(d), that the proposed modification meets the 
criteria for use of minor permit modification procedures and a request 
that such procedures be used; and
    (D) Completed forms for the permitting authority to use to notify 
the Administrator and affected States as required under Sec. 
70.8.
    (iii) EPA and affected State notification. Within 5 working days of 
receipt of a complete permit modification application, the permitting 
authority shall meet its obligation under Sec. 70.8 (a)(1) and 
(b)(1) to notify the Administrator and affected States of the requested 
permit modification. The permitting authority promptly shall send any 
notice required under Sec. 70.8(b)(2) to the Administrator.
    (iv) Timetable for issuance. The permitting authority may not issue 
a final permit modification until after EPA's 45-day review period or 
until EPA has notified the permitting authority that EPA will not object 
to issuance of the permit modification, whichever is first, although the 
permitting authority can approve the permit modification prior to that 
time. Within 90 days of the permitting authority's receipt of an 
application under minor permit modification procedures or 15 days after 
the end of the Administrator's 45-day review period under Sec. 
70.8(c), whichever is later, the permitting authority shall:
    (A) Issue the permit modification as proposed;
    (B) Deny the permit modification application;
    (C) Determine that the requested modification does not meet the 
minor permit modification criteria and should be reviewed under the 
significant modification procedures; or
    (D) Revise the draft permit modification and transmit to the 
Administrator the new proposed permit modification as required by 
Sec. 70.8(a) of this part.
    (v) Source's ability to make change. The State program may allow the 
source to make the change proposed in its minor permit modification 
application immediately after it files such application. After the 
source makes the change allowed by the preceding sentence, and until the 
permitting authority takes any of the actions specified in paragraphs 
(e)(2)(v) (A) through (C) of this section, the source must comply with 
both the applicable requirements governing the change and the proposed 
permit terms and conditions. During this time period, the source need 
not comply with the existing permit terms and conditions it seeks to 
modify. However, if the source fails to comply with its proposed permit 
terms and conditions during this time period, the existing permit terms 
and conditions it seeks to modify may be enforced against it.
    (vi) Permit shield. The permit shield under Sec. 70.6(f) 
of this part may not extend to minor permit modifications.

[[Page 231]]

    (3) Group processing of minor permit modifications. Consistent with 
this paragraph, the permitting authority may modify the procedure 
outlined in paragraph (e)(2) of this section to process groups of a 
source's applications for certain modifications eligible for minor 
permit modification processing.
    (i) Criteria. Group processing of modifications may be used only for 
those permit modifications:
    (A) That meet the criteria for minor permit modification procedures 
under paragraph (e)(2)(i)(A) of this section; and
    (B) That collectively are below the threshold level approved by the 
Administrator as part of the approved program. Unless the State sets an 
alternative threshold consistent with the criteria set forth in 
paragraphs (e)(3)(i)(B) (1) and (2) of this section, this threshold 
shall be 10 percent of the emissions allowed by the permit for the 
emissions unit for which the change is requested, 20 percent of the 
applicable definition of major source in Sec. 70.2 of this 
part, or 5 tons per year, whichever is least. In establishing any 
alternative threshold, the State shall consider:
    (1) Whether group processing of amounts below the threshold levels 
reasonably alleviates severe administrative burdens that would be 
imposed by immediate permit modification review, and
    (2) Whether individual processing of changes below the threshold 
levels would result in trivial environmental benefits.
    (ii) Application. An application requesting the use of group 
processing procedures shall meet the requirements of Sec. 
70.5(c) of this part and shall include the following:
    (A) A description of the change, the emissions resulting from the 
change, and any new applicable requirements that will apply if the 
change occurs.
    (B) The source's suggested draft permit.
    (C) Certification by a responsible official, consistent with 
Sec. 70.5(d) of this part, that the proposed modification 
meets the criteria for use of group processing procedures and a request 
that such procedures be used.
    (D) A list of the source's other pending applications awaiting group 
processing, and a determination of whether the requested modification, 
aggregated with these other applications, equals or exceeds the 
threshold set under paragraph (e)(3)(i)(B) of this section.
    (E) Certification, consistent with Sec. 70.5(d) of this 
part, that the source has notified EPA of the proposed modification. 
Such notification need only contain a brief description of the requested 
modification.
    (F) Completed forms for the permitting authority to use to notify 
the Administrator and affected States as required under Sec. 
70.8 of this part.
    (iii) EPA and affected State notification. On a quarterly basis or 
within 5 business days of receipt of an application demonstrating that 
the aggregate of a source's pending applications equals or exceeds the 
threshold level set under paragraph (e)(3)(i)(B) of this section, 
whichever is earlier, the permitting authority promptly shall meet its 
obligations under Sec.Sec. 70.8 (a)(1) and (b)(1) to 
notify the Administrator and affected States of the requested permit 
modifications. The permitting authority shall send any notice required 
under Sec. 70.8(b)(2) of this part to the Administrator.
    (iv) Timetable for issuance. The provisions of paragraph (e)(2)(iv) 
of this section shall apply to modifications eligible for group 
processing, except that the permitting authority shall take one of the 
actions specified in paragraphs (e)(2)(iv) (A) through (D) of this 
section within 180 days of receipt of the application or 15 days after 
the end of the Administrator's 45-day review period under Sec. 
70.8(c) of this part, whichever is later.
    (v) Source's ability to make change. The provisions of paragraph 
(e)(2)(v) of this section shall apply to modifications eligible for 
group processing.
    (vi) Permit shield. The provisions of paragraph (e)(2)(vi) of this 
section shall also apply to modifications eligible for group processing.
    (4) Significant modification procedures - (i) Criteria. 
Significant modification procedures shall be used for applications 
requesting permit modifications that do not qualify as minor permit 
modifications or as administrative amendments. The State

[[Page 232]]

program shall contain criteria for determining whether a change is 
significant. At a minimum, every significant change in existing 
monitoring permit terms or conditions and every relaxation of reporting 
or recordkeeping permit terms or conditions shall be considered 
significant. Nothing herein shall be construed to preclude the permittee 
from making changes consistent with this part that would render existing 
permit compliance terms and conditions irrelevant.
    (ii) The State program shall provide that significant permit 
modifications shall meet all requirements of this part, including those 
for applications, public participation, review by affected States, and 
review by EPA, as they apply to permit issuance and permit renewal. The 
permitting authority shall design and implement this review process to 
complete review on the majority of significant permit modifications 
within 9 months after receipt of a complete application.
    (f) Reopening for cause. (1) Each issued permit shall include 
provisions specifying the conditions under which the permit will be 
reopened prior to the expiration of the permit. A permit shall be 
reopened and revised under any of the following circumstances:
    (i) Additional applicable requirements under the Act become 
applicable to a major part 70 source with a remaining permit term of 3 
or more years. Such a reopening shall be completed not later than 18 
months after promulgation of the applicable requirement. No such 
reopening is required if the effective date of the requirement is later 
than the date on which the permit is due to expire, unless the original 
permit or any of its terms and conditions has been extended pursuant to 
Sec. 70.4(b)(10) (i) or (ii) of this part.
    (ii) Additional requirements (including excess emissions 
requirements) become applicable to an affected source under the acid 
rain program. Upon approval by the Administrator, excess emissions 
offset plans shall be deemed to be incorporated into the permit.
    (iii) The permitting authority or EPA determines that the permit 
contains a material mistake or that inaccurate statements were made in 
establishing the emissions standards or other terms or conditions of the 
permit.
    (iv) The Administrator or the permitting authority determines that 
the permit must be revised or revoked to assure compliance with the 
applicable requirements.
    (2) Proceedings to reopen and issue a permit shall follow the same 
procedures as apply to initial permit issuance and shall affect only 
those parts of the permit for which cause to reopen exists. Such 
reopening shall be made as expeditiously as practicable.
    (3) Reopenings under paragraph (f)(1) of this section shall not be 
initiated before a notice of such intent is provided to the part 70 
source by the permitting authority at least 30 days in advance of the 
date that the permit is to be reopened, except that the permitting 
authority may provide a shorter time period in the case of an emergency.
    (g) Reopenings for cause by EPA. (1) If the Administrator finds that 
cause exists to terminate, modify, or revoke and reissue a permit 
pursuant to paragraph (f) of this section, the Administrator will notify 
the permitting authority and the permittee of such finding in writing.
    (2) The permitting authority shall, within 90 days after receipt of 
such notification, forward to EPA a proposed determination of 
termination, modification, or revocation and reissuance, as appropriate. 
The Administrator may extend this 90-day period for an additional 90 
days if he finds that a new or revised permit application is necessary 
or that the permitting authority must require the permittee to submit 
additional information.
    (3) The Administrator will review the proposed determination from 
the permitting authority within 90 days of receipt.
    (4) The permitting authority shall have 90 days from receipt of an 
EPA objection to resolve any objection that EPA makes and to terminate, 
modify, or revoke and reissue the permit in accordance with the 
Administrator's objection.
    (5) If the permitting authority fails to submit a proposed 
determination pursuant to paragraph (g)(2) of this section or fails to 
resolve any objection

[[Page 233]]

pursuant to paragraph (g)(4) of this section, the Administrator will 
terminate, modify, or revoke and reissue the permit after taking the 
following actions:
    (i) Providing at least 30 days' notice to the 
permittee in writing of the reasons for any such action. This notice may 
be given during the procedures in paragraphs (g) (1) through (4) of this 
section.
    (ii) Providing the permittee an opportunity for comment on the 
Administrator's proposed action and an opportunity for a hearing.
    (h) Public participation. Except for modifications qualifying for 
minor permit modification procedures, all permit proceedings, including 
initial permit issuance, significant modifications, and renewals, shall 
provide adequate procedures for public notice including offering an 
opportunity for public comment and a hearing on the draft permit. These 
procedures shall include the following:
    (1) Notice shall be given: by publication in a newspaper of general 
circulation in the area where the source is located or in a State 
publication designed to give general public notice; to persons on a 
mailing list developed by the permitting authority, including those who 
request in writing to be on the list; and by other means if necessary to 
assure adequate notice to the affected public;
    (2) The notice shall identify the affected facility; the name and 
address of the permittee; the name and address of the permitting 
authority processing the permit; the activity or activities involved in 
the permit action; the emissions change involved in any permit 
modification; the name, address, and telephone number of a person from 
whom interested persons may obtain additional information, including 
copies of the permit draft, the application, all relevant supporting 
materials, including those set forth in Sec. 70.4(b)(3)(viii) 
of this part, and all other materials available to the permitting 
authority that are relevant to the permit decision; a brief description 
of the comment procedures required by this part; and the time and place 
of any hearing that may be held, including a statement of procedures to 
request a hearing (unless a hearing has already been scheduled);
    (3) The permitting authority shall provide such notice and 
opportunity for participation by affected States as is provided for by 
Sec. 70.8 of this part;
    (4) Timing. The permitting authority shall provide at least 30 days 
for public comment and shall give notice of any public hearing at least 
30 days in advance of the hearing.
    (5) The permitting authority shall keep a record of the commenters 
and also of the issues raised during the public participation process so 
that the Administrator may fulfill his obligation under section 
505(b)(2) of the Act to determine whether a citizen petition may be 
granted, and such records shall be available to the public.