Sec. 70.8  Permit review by EPA and affected States.

    (a) Transmission of information to the Administrator. (1) The permit 
program shall require that the permitting authority provide to the 
Administrator a copy of each permit application (including any 
application for permit modification), each proposed permit, and each 
final part 70 permit. The applicant may be required by the permitting 
authority to provide a copy of the permit application (including the 
compliance plan) directly to the Administrator. Upon agreement with the 
Administrator, the permitting authority may submit to the Administrator 
a permit application summary form and any relevant portion of the permit 
application and compliance plan, in place of the complete permit 
application and compliance plan. To the extent practicable, the 
preceding information shall be provided in computer-readable format 
compatible with EPA's national database management system.
    (2) The Administrator may waive the requirements of paragraphs 
(a)(1) and (b)(1) of this section for any category of sources (including 
any class, type, or size within such category) other than major sources 
according to the following:
    (i) By regulation for a category of sources nationwide, or

[[Page 234]]

    (ii) At the time of approval of a State program for a category of 
sources covered by an individual permitting program.
    (3) Each State permitting authority shall keep for 5 years such 
records and submit to the Administrator such information as the 
Administrator may reasonably require to ascertain whether the State 
program complies with the requirements of the Act or of this part.
    (b) Review by affected States. (1) The permit program shall provide 
that the permitting authority give notice of each draft permit to any 
affected State on or before the time that the permitting authority 
provides this notice to the public under Sec. 70.7(h) of this 
part, except to the extent Sec. 70.7(e) (2) or (3) of this 
part requires the timing of the notice to be different.
    (2) The permit program shall provide that the permitting authority, 
as part of the submittal of the proposed permit to the Administrator [or 
as soon as possible after the submittal for minor permit modification 
procedures allowed under Sec. 70.7(e) (2) or (3) of this 
part], shall notify the Administrator and any affected State in writing 
of any refusal by the permitting authority to accept all recommendations 
for the proposed permit that the affected State submitted during the 
public or affected State review period. The notice shall include the 
permitting authority's reasons for not accepting any such 
recommendation. The permitting authority is not required to accept 
recommendations that are not based on applicable requirements or the 
requirements of this part.
    (c) EPA objection. (1) The Administrator will object to the issuance 
of any proposed permit determined by the Administrator not to be in 
compliance with applicable requirements or requirements under this part. 
No permit for which an application must be transmitted to the 
Administrator under paragraph (a) of this section shall be issued if the 
Administrator objects to its issuance in writing within 45 days of 
receipt of the proposed permit and all necessary supporting information.
    (2) Any EPA objection under paragraph (c)(1) of this section shall 
include a statement of the Administrator's reasons for objection and a 
description of the terms and conditions that the permit must include to 
respond to the objections. The Administrator will provide the permit 
applicant a copy of the objection.
    (3) Failure of the permitting authority to do any of the following 
also shall constitute grounds for an objection:
    (i) Comply with paragraphs (a) or (b) of this section;
    (ii) Submit any information necessary to review adequately the 
proposed permit; or
    (iii) Process the permit under the procedures approved to meet 
Sec. 70.7(h) of this part except for minor permit 
modifications.
    (4) If the permitting authority fails, within 90 days after the date 
of an objection under paragraph (c)(1) of this section, to revise and 
submit a proposed permit in response to the objection, the Administrator 
will issue or deny the permit in accordance with the requirements of the 
Federal program promulgated under title V of this Act.
    (d) Public petitions to the Administrator. The program shall provide 
that, if the Administrator does not object in writing under paragraph 
(c) of this section, any person may petition the Administrator within 60 
days after the expiration of the Administrator's 45-day review period to 
make such objection. Any such petition shall be based only on objections 
to the permit that were raised with reasonable specificity during the 
public comment period provided for in Sec. 70.7(h) of this 
part, unless the petitioner demonstrates that it was impracticable to 
raise such objections within such period, or unless the grounds for such 
objection arose after such period. If the Administrator objects to the 
permit as a result of a petition filed under this paragraph, the 
permitting authority shall not issue the permit until EPA's objection 
has been resolved, except that a petition for review does not stay the 
effectiveness of a permit or its requirements if the permit was issued 
after the end of the 45-day review period and prior to an EPA objection. 
If the permitting authority has issued a permit prior to receipt of an 
EPA objection under this paragraph, the Administrator will modify, 
terminate, or revoke such permit, and shall do so consistent with the

[[Page 235]]

procedures in Sec. 70.7(g) (4) or (5) (i) and (ii) of this 
part except in unusual circumstances, and the permitting authority may 
thereafter issue only a revised permit that satisfies EPA's objection. 
In any case, the source will not be in violation of the requirement to 
have submitted a timely and complete application.
    (e) Prohibition on default issuance. Consistent with Sec. 
70.4(b)(3)(ix) of this part, for the purposes of Federal law and title V 
of the Act, no State program may provide that a part 70 permit 
(including a permit renewal or modification) will issue until affected 
States and EPA have had an opportunity to review the proposed permit as 
required under this section. When the program is submitted for EPA 
review, the State Attorney General or independent legal counsel shall 
certify that no applicable provision of State law requires that a part 
70 permit or renewal be issued after a certain time if the permitting 
authority has failed to take action on the application (or includes any 
other similar provision providing for default issuance of a permit), 
unless EPA has waived such review for EPA and affected States.