[Code of Federal Regulations]
[Title 40, Volume 14]
[Revised as of July 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 40CFR74.16]
[Page 181-182]
TITLE 40--PROTECTION OF ENVIRONMENT
CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)
PART 74--SULFUR DIOXIDE OPT-INS--Table of Contents
Subpart B--Permitting Procedures
Sec. 74.16 Application requirements for combustion sources.
(a) Opt-in permit application. Each complete opt-in permit
application for a combustion source shall contain the following elements
in a format prescribed by the Administrator:
(1) Identification of the combustion source, including company name,
plant name, plant site address, mailing address, description of the
combustion source, and information and diagrams on the combustion
source's configuration;
(2) Identification of the designated representative, including name,
address, telephone number, and facsimile number;
(3) The year and month the combustion source commenced operation;
(4) The number of hours the combustion source operated in the six
months preceding the opt-in permit application and supporting
documentation;
(5) The baseline or alternative baseline data under Sec. 74.20;
(6) The actual SO2 emissions rate under Sec. 74.22;
(7) The allowable 1985 SO2 emissions rate under
Sec. 74.23;
(8) The current allowable SO2 emissions rate under
Sec. 74.24;
(9) The current promulgated SO2 emissions rate under
Sec. 74.25;
(10) If the combustion source seeks to qualify for a transfer of
allowances from the replacement of thermal energy, a thermal energy plan
as provided in Sec. 74.47 for combustion sources; and
(11) A statement whether the combustion source was previously an
affected unit under this part;
(12) A statement that the combustion source is not an affected unit
under Sec. 72.6 of this chapter and does not have an exemption under
Sec. 72.7, Sec. 72.8, or Sec. 72.14 of this chapter;
(13) A complete compliance plan for SO2 under Sec. 72.40
of this chapter; and
(14) The following statement signed by the designated representative
of the
[[Page 182]]
combustion source: ``I certify that the data submitted under subpart C
of part 74 reflects actual operations of the combustion source and has
not been adjusted in any way.''
(b) Accompanying documents. The designated representative of the
combustion source shall submit a monitoring plan in accordance with
Sec. 74.61.
[60 FR 17115, Apr. 4, 1995, as amended at 63 FR 18841, Apr. 16, 1998]