[Code of Federal Regulations]
[Title 40, Volume 18]
[Revised as of July 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 40CFR93.117]
[Page 560]
TITLE 40--PROTECTION OF ENVIRONMENT
CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)
PART 93--DETERMINING CONFORMITY OF FEDERAL ACTIONS TO STATE OR FEDERAL
IMPLEMENTATION PLANS--Table of Contents
Subpart A--Conformity to State or Federal Implementation Plans of
Transportation Plans, Programs, and Projects Developed, Funded or
Approved Under Title 23 U.S.C. or the Federal Transit Laws
Sec. 93.117 Criteria and procedures: Compliance with PM10
control measures.
The FHWA/FTA project must comply with PM10 control
measures in the applicable implementation plan. This criterion is
satisfied if the project-level conformity determination contains a
written commitment from the project sponsor to include in the final
plans, specifications, and estimates for the project those control
measures (for the purpose of limiting PM10 emissions from the
construction activities and/or normal use and operation associated with
the project) that are contained in the applicable implementation plan.