Sec. 97.21 Submission of NOX Budget permit applications.
(a) Duty to apply. The NOX authorized account
representative of any NOX Budget source required to have a
federally enforceable permit shall submit to the permitting authority a
complete NOX Budget permit application under Sec. 97.22 by
the applicable deadline in paragraph (b) of this section.
(b)(1) For NOX Budget sources required to have a title V
operating permit:
(i) For any source, with one or more NOX Budget units
under Sec. 97.4(a) that commence operation before January 1, 2001, the
NOX authorized account representative shall submit a complete
NOX Budget permit application under Sec. 97.22 covering such
NOX Budget units to the permitting authority at least 18
months (or such lesser time provided by the permitting authority) before
May 31, 2004.
(ii) For any source, with any NOX Budget unit under
Sec. 97.4(a) that commences operation on or after January 1, 2001, the
NOX authorized account representative shall submit a complete
NOX Budget permit application under Sec. 97.22 covering such
NOX Budget unit to the permitting authority at least 18
months (or such lesser time provided by the permitting authority) before
the later of May 31, 2004 or the date on which the NOX Budget
unit commences operation.
(2) For NOX Budget sources required to have a non-title V
permit:
(i) For any source, with one or more NOX Budget units
under Sec. 97.4(a) that commence operation before January 1, 2001, the
NOX authorized account representative shall submit a complete
NOX Budget permit application under Sec. 97.22 covering such
NOX Budget units to the permitting authority at least 18
months (or such lesser time provided by the permitting authority) before
May 31, 2004.
(ii) For any source, with any NOX Budget unit under
Sec. 97.4(a) that commences operation on or after January 1, 2001, the
NOX authorized account representative shall submit a complete
NOX Budget permit application under Sec. 97.22 covering such
NOX Budget unit to the permitting authority at least 18
months (or such lesser time provided by the permitting authority) before
the later of May 31, 2004 or the date on which the NOX Budget
unit commences operation.
(c) Duty to reapply. (1) For a NOX Budget source required
to have a title V operating permit, the NOX authorized
account representative shall submit a complete NOX Budget
permit application under Sec. 97.22 for the NOX Budget source
covering the NOX Budget units at the source in accordance
with the permitting authority's title V operating permits regulations
addressing operating permit renewal.
(2) For a NOX Budget source required to have a non-title
V permit, the NOX authorized account representative shall
submit a complete NOX Budget permit application under
Sec. 97.22 for the NOX Budget source covering the
NOX Budget units at the source in accordance with the
permitting authority's non-title V permits regulations addressing permit
renewal.
[65 FR 2727, Jan. 18, 2000, as amended at 67 FR 21529, Apr. 30, 2002]