[Code of Federal Regulations]
[Title 41, Volume 3]
[Revised as of July 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 41CFR102-74.125]

[Page 184]
 
           TITLE 41--PUBLIC CONTRACTS AND PROPERTY MANAGEMENT
 
               CHAPTER 102--FEDERAL MANAGEMENT REGULATION
 
PART 102-74--FACILITY MANAGEMENT--Table of Contents
 
                     Subpart B--Facility Management
 
Sec. 102-74.125  Are prospectuses required for reimbursable alteration 
projects?

    A project which is to be financed in whole or in part from funds 
appropriated to the requesting agency may be performed without a 
prospectus if:
    (a) Payment is made from agency appropriations that are not subject 
to Section 7 of the Public Buildings Act of 1959 (40 U.S.C. 606); and
    (b) GSA's portion of the cost, if any, does not exceed the 
prospectus threshold.