Sec. 105-72.701  Termination.

    (a) Awards may be terminated in whole or in part only if paragraph 
(a)(1), (2) or (3) of this section apply.
    (1) By the Federal awarding agency, if a recipient materially fails 
to comply with the terms and conditions of an award.
    (2) By the Federal awarding agency with the consent of the 
recipient, in which case the two parties shall agree upon the 
termination conditions, including the effective date and, in the case of 
partial termination, the portion to be terminated.
    (3) By the recipient upon sending to the Federal awarding agency 
written notification setting forth the reasons for such termination, the 
effective date, and, in the case of partial termination, the portion to 
be terminated. However, if the Federal awarding agency determines in the 
case of partial termination that the reduced or modified portion of the 
grant will not accomplish the purposes for which the grant was made, it 
may terminate the grant in its entirety under either paragraphs (a) (1) 
or (2).
    (b) If costs are allowed under an award, the responsibilities of the 
recipient referred to in Sec. 105-72.801(a), including those for 
property management as applicable, shall be considered in the 
termination of the award, and provision shall be made for continuing 
responsibilities of the recipient after termination, as appropriate.