Sec. 1355.56  Failure to meet the conditions of the approved APD.

    (a) If ACF finds that the State fails to meet any of the conditions 
cited in Sec. 1355.53, or to substantially comply with the criteria, 
requirements and other undertakings prescribed by the approved APD, 
approval of the APD may be suspended.
    (b) If the approval of an APD is suspended during the planning, 
design, development, installation, or operation of the system:
    (1) The State will be given written notice of the suspension. This 
notice shall state:
    (i) The reason for the suspension,
    (ii) The date of the suspension,
    (iii) Whether the suspended system complies with criteria for 50 
percent FFP, and
    (iv) The actions required by the State for future enhanced funding.
    (2) The suspension will be effective as of the date the State failed 
to comply with the approved APD;
    (3) The suspension shall remain in effect until ACF determines that 
such system complies with prescribed criteria, requirements, and other 
undertakings for future Federal funding.
    (4) Should a State cease development of an approved system, either 
by voluntary withdrawal or as a result of Federal suspension, all 
Federal incentive funds invested to date that exceed the normal 
administrative FFP rate (50 percent) will be subject to recoupment.