Sec. 174.055  Calculation of wind heeling moment (Hm).

    (a) The wind heeling moment (Hm) of a unit in a given normal 
operating condition or severe storm condition is the sum of the 
individual wind heeling moments (H) calculated for each of the exposed 
surfaces on the unit; i.e., Hm=[Sigma] H.
    (b) Each wind heeling moment (H) must be calculated using the 
equation:

H=k(v)2(Ch)(Cs)(A)(h)

where--

(1) H=wind heeling moment for an exposed surface on the unit in foot-
pounds (kilogram-meters);
(2) k=0.00338 lb./(ft.2-knots2) (0.0623 (kg-
sec2)/m4);
(3) v=wind velocity of--
(i) 70 knots (36 meters per second) for normal operating conditions.
(ii) 100 knots (51.5 meters per second) for severe storm conditions.
(iii) 50 knots (25.8 meters per second) for damage conditions.
(4) A=projected area in square feet (squrae meters) of an exposed 
surface on the unit;
(5) Ch=height coefficient for ``A'' from Table 174.055(a);
(6) Cs=shape coefficient for ``A'' from Table 174.055(b); and
(7) h=the vertical distance in feet (meters) from the center of lateral 
resistance of the underwater hull to the center of wind pressure on 
``A''.

    (c) When calculating ``A'' in the equation described in paragraph 
(b) of this section--
    (1) The projected area of each column or leg; if the unit has 
columns or legs, must not include shielding allowances;
    (2) Each area exposed as a result of heel must be included;
    (3) The projected area of a cluster of deck houses may be used 
instead of the projected area of each individual deck house in the 
cluster; and
    (4) The projected area of open truss work may be calculated by 
taking 30% of the projected areas of both the front and back sides of 
the open truss work rather than by determining the projected area of 
each structural member of the truss work.

                                           Table 174.055(a)--Ch Values
----------------------------------------------------------------------------------------------------------------
                           Feet                                                Meters
---------------------------------------------------------------------------------------------------------   Ch.
                Over                     Not exceeding               Over              Not exceeding
----------------------------------------------------------------------------------------------------------------
                 0                             50                    0.0                    15.3            1.00
                 50                           100                    15.3                   30.5            1.10
                100                           150                    30.5                   46.0            1.20
                150                           200                    46.0                   61.0            1.30
                200                           250                    61.0                   76.0            1.37
                250                           300                    76.0                   91.5            1.43
                300                           350                    91.5                  106.5            1.48
                350                           400                   106.5            2.0................    1.52
                400                           450                   122.0                  137.0            1.56
                450                           500                   137.0                  152.5            1.60
                500                           550                   152.5                  167.5            1.63
                550                           600                   167.5                  183.0            1.67
                600                           650                   183.0                  198.0            1.70
                650                           700                   198.0                  213.5            1.72
                700                           750                   213.5                  228.5            1.75
                750                           800                   228.5                  244.0            1.77
                800                           850                   244.0                  256.0            1.79
Above 850..........................                               Above 256                                 1.80
----------------------------------------------------------------------------------------------------------------
Note: The ``Ch'' value in this table, used in the equation described in section Sec.  174.055(b), corresponds to
  the value of the vertical distance in feet (meters) from the water surface at the design draft of the unit to
  the center of area of the ``A'' value used in the equation.


                       Table 174.055(b)--Cs Values
------------------------------------------------------------------------
                              Shape                                 Cs.
------------------------------------------------------------------------
Cylindrical shapes...............................................    0.5
Hull (surface type)..............................................    1.0
Deckhouse........................................................    1.0
Cluster of deckhouses............................................    1.1
Isolated structural shapes (cranes, angles, channels, beams,         1.5
 etc.)...........................................................
Under deck areas (smooth surfaces)...............................    1.0
Under deck areas (exposed beams and girders).....................    1.3
Rig derrick (each face and open truss works).....................   1.25
------------------------------------------------------------------------
Note: The ``Cs'' value in this table, used in the equation described in
  Sec.  174.055(b), corresponds to the shape of the projected ``A'' in
  the equation.