            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
                CHAPTER 1--FEDERAL ACQUISITION REGULATION
 
PART 11_DESCRIBING AGENCY NEEDS--Table of Contents
 
             Subpart 11.4_Delivery or Performance Schedules
 
Sec.  11.404  Contract clauses.

    (a) Supplies or services. (1) The contracting officer may use a time 
of delivery clause to set forth a required delivery schedule and to 
allow an offeror to propose an alternative delivery schedule. The 
clauses and their alternates may be used in solicitations and contracts 
for other than construction and architect-engineering substantially as 
shown, or they may be changed or new clauses written.
    (2) The contracting officer may insert in solicitations and 
contracts other than those for construction and architect-engineering, a 
clause substantially the same as the clause at 52.211-8, Time of 
Delivery, if the Government requires delivery by a particular time and 
the delivery schedule is to be based on the date of the contract. If the 
delivery schedule is expressed in terms of specific calendar dates or 
specific periods and is based on an assumed date of award, the 
contracting officer may use the clause with its Alternate I. If the 
delivery schedule is expressed in terms of specific calendar dates or 
specific periods and is based on an assumed date the contractor will 
receive notice of award, the contracting officer may use the clause with 
its Alternate II. If the delivery schedule is to be based on the actual 
date the contractor receives a written notice of award, the contracting 
officer may use the clause with its Alternate III.
    (3) The contracting officer may insert in solicitations and 
contracts other than those for construction and architect-engineering, a 
clause substantially the same as the clause at 52.211-9, Desired and 
Required Time of Delivery, if the Government desires delivery by a 
certain time but requires delivery by a specified later time, and the 
delivery schedule is to be based on the date of the contract. If the 
delivery schedule is expressed in terms of specific calendar dates or 
specific periods and is based on an assumed date of award, the 
contracting officer may use the clause with its Alternate I. If the 
delivery schedule is expressed in terms of specific calendar dates or 
specific periods and is based on an assumed date the contractor will 
receive notice of award, the contracting officer may use the clause with 
its Alternate II. If the delivery schedule is to be based on the actual 
date the contractor receives a written notice of award, the contracting 
officer may use the clause with its Alternate III.
    (b) Construction. The contracting officer shall insert the clause at 
52.211-10, Commencement, Prosecution, and Completion of Work, in 
solicitations and contracts when a fixed-price construction contract is 
contemplated. The clause may be changed to accommodate the issuance of 
orders under indefinite-delivery contracts. If the completion date is 
expressed as a specific calendar date, computed on the basis of the 
contractor receiving the notice to

[[Page 180]]

proceed by a certain day, the contracting officer may use the clause 
with its Alternate I.

[48 FR 42159, Sept. 19, 1983, as amended at 56 FR 41732, Aug. 22, 1991. 
Redesignated and amended at 60 FR 48241, Sept. 18, 1995]