            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
                CHAPTER 1--FEDERAL ACQUISITION REGULATION
 
PART 11_DESCRIBING AGENCY NEEDS--Table of Contents
 
                     Subpart 11.5_Liquidated Damages
 
Sec.  11.503  Contract clauses.

    (a) Use the clause at 52.211-11, Liquidated Damages--Supplies, 
Services, or Research and Development, in fixed-price solicitations and 
contracts for supplies, services, or research and development when the 
contracting officer determines that liquidated damages are appropriate 
(see 11.501(a)).
    (b) Use the clause at 52.211-12, Liquidated Damages--Construction, 
in solicitations and contracts for construction, other than cost-plus-
fixed-fee,

[[Page 181]]

when the contracting officer determines that liquidated damages are 
appropriate (see 11.501(a)). If the contract specifies more than one 
completion date for separate parts or stages of the work, revise 
paragraph (a) of the clause to state the amount of liquidated damages 
for delay of each separate part or stage of the work.
    (c) Use the clause at 52.211-13, Time Extensions, in solicitations 
and contracts for construction that use the clause at 52.211-12, 
Liquidated Damages--Construction, when that clause has been revised as 
provided in paragraph (b) of this section.