[Code of Federal Regulations]
[Title 48, Volume 1]
[Revised as of October 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 48CFR22.103-5]

[Page 396]
 
            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
                CHAPTER 1--FEDERAL ACQUISITION REGULATION
 
PART 22_APPLICATION OF LABOR LAWS TO GOVERNMENT ACQUISITIONS--Table of Contents
 
                    Subpart 22.1_Basic Labor Policies
 
Sec.  22.103-5  Contract clauses.

    (a) The contracting officer shall insert the clause 52.222-1, Notice 
to the Government of Labor Disputes, in solicitations and contracts that 
involve programs or requirements that have been designated under 22.101-
1(e).
    (b) The contracting officer shall include the clause at 52.222-2, 
Payment for Overtime Premiums, in solicitations and contracts when a 
cost-reimbursement contract is contemplated and the contract amount is 
expected to be over $100,000; unless (a) a cost-reimbursement contract 
for operation of vessels is contemplated, or (b) a cost-plus-incentive-
fee contract that will provide a swing from the target fee of at least 
plus or minus 3 percent and a contractor's share of at least 10 percent 
is contemplated.