            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
                CHAPTER 1--FEDERAL ACQUISITION REGULATION
 
PART 36_CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS--Table of Contents
 
      Subpart 36.2_Special Aspects of Contracting for Construction
 
Sec.  36.208  Concurrent performance of firm-fixed-price and other types 
of construction contracts.

    In view of potential labor and administrative problems, cost-plus-
fixed-fee, price-incentive, or other types of contracts with cost 
variation or cost adjustment features shall not be permitted 
concurrently, at the same work site, with firm-fixed-price, lump sum,

[[Page 716]]

or unit price contracts except with the prior approval of the head of 
the contracting activity.