Sec.  36.212  Preconstruction orientation.

    (a) The contracting officer will inform the successful offeror of 
significant matters of interest, including--(1) statutory matters such 
as labor standards (subpart 22.4), and subcontracting plan requirements 
(subpart 19.7); and (2) other matters of significant interest, including 
who has authority to decide matters such as contractual, administrative 
(e.g., security, safety, and fire and environmental protection), and 
construction responsibilities.
    (b) As appropriate, the contracting officer may issue an explanatory 
letter or conduct a preconstruction conference.
    (c) If a preconstruction conference is to be held, the contracting 
officer shall--
    (1) Conduct the conference prior to the start of construction at the 
work site;
    (2) Notify the successful offeror of the date, time, and location of 
the conference (see 36.522); and
    (3) Inform the successful offeror of the proposed agenda and any 
need for attendance by subcontractors.

[59 FR 67049, Dec. 28, 1994]