Sec.  36.303  Procedures.

    One solicitation may be issued covering both phases, or two 
solicitations may be issued in sequence. Proposals will be evaluated in 
Phase One to determine which offerors will submit proposals for Phase 
Two. One contract will be awarded using competitive negotiation.