Sec.  36.512  Cleaning up.

    The contracting officer shall insert the clause at 52.236-12, 
Cleaning Up, in solicitations and contracts when a fixed-price 
construction contract or a fixed-price dismantling, demolition, or 
removal of improvements contract is contemplated and the contract amount 
is expected to exceed the simplified acquisition threshold. The 
contracting officer may insert the clause in solicitations and contracts 
when a fixed-price construction or a fixed-price contract for 
dismantling, demolition, or

[[Page 722]]

removal of improvements is contemplated and the contract amount is 
expected to be at or below the simplified acquisition threshold.

[48 FR 42356, Sept. 19, 1983, as amended at 60 FR 34759, July 3, 1995]