PART 36_CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS--Table of Contents
 
                      Subpart 36.5_Contract Clauses
 
Sec.  36.515  Schedules for construction contracts.

    The contracting officer may insert the clause at 52.236-15, 
Schedules for Construction Contracts, in solicitations and contracts 
when a fixed-price construction contract is contemplated, the contract 
amount is expected to exceed the simplified acquisition threshold, and 
the period of actual work performance exceeds 60 days. This clause may 
also be inserted in such solicitations and contracts when work 
performance is expected to last less than 60 days and an unusual 
situation exists that warrants imposition of the requirements. This 
clause should not be used in the same contract with clauses covering 
other management approaches for ensuring that a contractor makes 
adequate progress.

[48 FR 42356, Sept. 19, 1983, as amended at 60 FR 34759, July 3, 1995]