Sec.  43.104  Notification of contract changes.

    (a) When a contractor considers that the Government has effected or 
may effect a change in the contract that has not been identified as such 
in writing and signed by the contracting officer, it is necessary that 
the contractor notify the Government in writing as soon as possible. 
This will permit the Government to evaluate the alleged change and (1) 
confirm that it is a change, direct the mode of further performance, and 
plan for its funding; (2) countermand the alleged change; or (3) notify 
the contractor that no change is considered to have occurred.
    (b) The clause at 52.243-7, Notification of Changes, which is 
prescribed in 43.107, (1) incorporates the policy expressed in paragraph 
(a) above; (2) requires the contractor to notify the Government promptly 
of any Government conduct that the contractor considers a change to the 
contract, and (3) specifies the responsibilities of the contractor and 
the Government with respect to such notifications.

[48 FR 42386, Sept. 19, 1983, as amended at 56 FR 41744, Aug. 22, 1991]