[Code of Federal Regulations]
[Title 48, Volume 1]
[Revised as of October 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 48CFR48]

[Page 897-899]
 
            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
                CHAPTER 1--FEDERAL ACQUISITION REGULATION
 
PART 48_VALUE ENGINEERING--Table of Contents
 
Sec.  48.001  Definitions.

    As used in this subpart--
    Acquisition savings means savings resulting from the application of 
a value engineering change proposal (VECP) to contracts awarded by the 
same contracting office of its successor for essentially the same unit. 
Acquisition savings include--
    (1) Instant contract savings, that are the net cost reductions on 
the contract under which the VECP is submitted and accepted, and that 
are equal to the instant unit cost reduction multiplied by the number of 
instant contract units affected by the VECP, less the contractor's 
allowable development and implementation costs;
    (2) Concurrent contract savings, that are net reductions in the 
prices of other contracts that are definitized and

[[Page 898]]

ongoing at the time the VECP is accepted; and
    (3) Future contract savings, that are the product of the future unit 
cost reduction multiplied by the number of future contract units in the 
sharing base. On an instant contract, future contract savings include 
savings on increases in quantities after VECP acceptance that are due to 
contract modifications, exercise of options, additional orders, and 
funding of subsequent year requirements on a multiyear contract.
    Collateral costs means agency costs of operation, maintenance 
logistic support, or Government-furnished property.
    Collateral savings means those measurable net reductions resulting 
from a VECP in the agency's overall projected collateral costs, 
exclusive of acquisition savings, whether or not the acquisition cost 
changes.
    Contracting office includes any contracting office that the 
acquisition is transferred to, such as another branch of the agency or 
another agency's office that is performing a joint acquisition action.
    Contractor's development and implementation costs means those costs 
the contractor incurs on a VECP specifically in developing, testing, 
preparing, and submitting the VECP, as well as those costs the 
contractor incurs to make the contractual changes required by Government 
acceptance of a VECP.
    Future unit cost reduction means the instant unit cost reduction 
adjusted as the contracting officer considers necessary for projected 
learning or changes in quantity during the sharing period. It is 
calculated at the time the VECP is accepted and applies either (1) 
throughout the sharing period, unless the contracting officer decides 
that recalculation is necessary because conditions are significantly 
different from those previously anticipated or (2) to the calculation of 
a lump-sum payment, that cannot later be revised.
    Government costs means those agency costs that result directly from 
developing and implementing the VECP, such as any net increases in the 
cost of testing, operations, maintenance, and logistics support. The 
term does not include the normal administrative costs of processing the 
VECP or any increase in instant contract cost or price resulting from 
negative instant contract savings, except that for use in 52.248-3, see 
the definition at 52.248-3(b).
    Instant contract means the contract under which the VECP is 
submitted. It does not include increases in quantities after acceptance 
of the VECP that are due to contract modifications, exercise of options, 
or additional orders. If the contract is a multiyear contract, the term 
does not include quantities funded after VECP acceptance. In a fixed-
price contract with prospective price redetermination, the term refers 
to the period for which firm prices have been established.
    Instant unit cost reduction means the amount of the decrease in unit 
cost of performance (without deducting any contractor's development or 
implementation costs) resulting from using the VECP on the instant 
contract. In service contracts, the instant unit cost reduction is 
normally equal to the number of hours per line-item task saved by using 
the VECP on the instant contract, multiplied by the appropriate contract 
labor rate.
    Negative instant contract savings means the increase in the instant 
contract cost or price when the acceptance of a VECP results in an 
excess of the contractor's allowable development and implementation 
costs over the product of the instant unit cost reduction multiplied by 
the number of instant contract units affected.
    Net acquisition savings means total acquisition savings, including 
instant, concurrent, and future contract savings, less Government costs.
    Sharing base means the number of affected end items on contracts of 
the contracting office accepting the VECP.
    Sharing period means the period beginning with acceptance of the 
first unit incorporating the VECP and ending at a calendar date or event 
determined by the contracting officer for each VECP.
    Unit means the item or task to which the contracting officer and the 
contractor agree the VECP applies.
    Value engineering proposal means, in connection with an A-E 
contract, a

[[Page 899]]

change proposal developed by employees of the Federal Government or 
contractor value engineering personnel under contract to an agency to 
provide value engineering services for the contract or program.

[48 FR 42443, Sept. 19, 1983, as amended at 54 FR 5057, Jan. 31, 1989; 
55 FR 3887, Feb. 5, 1990; 61 FR 39220, July 26, 1996; 64 FR 51847, Sept. 
24, 1999; 66 FR 2134, Jan. 10, 2001]