PART 49_TERMINATION OF CONTRACTS--Table of Contents
 
                     Subpart 49.1_General Principles
 
Sec.  49.105-4  Cleanup of construction site.

    In the case of terminated construction contracts, the contracting 
officer shall direct action to ensure the cleanup of the site, 
protection of serviceable materials, removal of hazards, and other 
action necessary to leave a safe and healthful site.