[Code of Federal Regulations] [Title 48, Volume 1] [Revised as of October 1, 2003] From the U.S. Government Printing Office via GPO Access [CITE: 48CFR49] [Page 914] TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM CHAPTER 1--FEDERAL ACQUISITION REGULATION PART 49_TERMINATION OF CONTRACTS--Table of Contents Subpart 49.1_General Principles Sec. 49.108-6 Delay in settling subcontractor settlement proposals. When a prime contractor's inability to settle with a subcontractor delays the settlement of the prime contract, the TCO may settle with the prime contractor. The TCO shall except the subcontractor settlement proposal from the settlement in whole or part and reserve the rights of the Government and the prime contractor with respect to the subcontractor proposal.