Sec.  49.109-5  Partial settlements.

    The TCO should attempt to settle in one agreement all rights and 
liabilities of the parties under the contract except those arising from 
any continued portion of the contract. Generally, the TCO shall not 
attempt to make partial settlements covering particular items of the 
prime contractor's settlement proposal. However, when a TCO cannot 
promptly complete settlement under the terminated contract, a partial 
settlement may be entered into if (a) the issues on which agreement has 
been reached are clearly severable from other issues and (b) the partial 
settlement will not prejudice the Government's or contractor's interests 
in disposing of the unsettled part of the settlement proposal.