Sec.  49.114  Unsettled contract changes.

    (a) Before settlement of a completely terminated contract, the TCO 
shall obtain from the contracting office a list of all related unsettled 
contract changes. The TCO shall settle, as part of final settlement, all 
unsettled contract changes after obtaining the recommendations of the 
contracting office concerning the changes.
    (b) When the contract has been partially terminated, any outstanding 
unsettled contract changes will usually be handled by the contracting 
officer. However, the contracting officer may delegate this function to 
the TCO.