[Code of Federal Regulations] [Title 49, Volume 3] [Revised as of October 1, 2003] From the U.S. Government Printing Office via GPO Access [CITE: 49CFR192.150] [Page 41-42] TITLE 49--TRANSPORTATION CHAPTER I--RESEARCH AND SPECIAL PROGRAMS ADMINISTRATION, DEPARTMENT OF TRANSPORTATION (CONTINUED) PART 192--TRANSPORTATION OF NATURAL AND OTHER GAS BY PIPELINE: MINIMUM FEDERAL SAFETY STANDARDS--Table of Contents Subpart D--Design of Pipeline Components Sec. 192.150 Passage of internal inspection devices. (a) Except as provided in paragraphs (b) and (c) of this section, each new transmission line and each line section of a transmission line where the line pipe, valve, fitting, or other line component is replaced must be designed and constructed to accommodate the passage of instrumented internal inspection devices. (b) This section does not apply to: (1) Manifolds; (2) Station piping such as at compressor stations, meter stations, or regulator stations; (3) Piping associated with storage facilities, other than a continuous run of transmission line between a compressor station and storage facilities; (4) Cross-overs; (5) Sizes of pipe for which an instrumented internal inspection device is not commercially available; (6) Transmission lines, operated in conjunction with a distribution system which are installed in Class 4 locations; (7) Offshore pipelines, other than transmission lines 10 inches (254 millimeters) or greater in nominal diameter, that transport gas to onshore facilities; and (8) Other piping that, under Sec. 190.9 of this chapter, the Administrator finds in a particular case would be impracticable to design and construct to accommodate the passage of instrumented internal inspection devices. (c) An operator encountering emergencies, construction time constraints or other unforeseen construction problems need not construct a new or replacement segment of a transmission line to meet paragraph (a) of this section, if the operator determines and documents why an impracticability prohibits compliance with paragraph (a) of this section. Within 30 days after discovering the emergency or construction problem the operator must petition, under Sec. 190.9 of this chapter, for approval that design and construction to accommodate passage of instrumented internal inspection devices would be impracticable. If the petition is denied, within 1 year after the date of the notice of the denial, the operator must modify that segment to allow [[Page 42]] passage of instrumented internal inspection devices. [Amdt. 192-72, 59 FR 17281, Apr. 12, 1994, as amended by Amdt. 192-85, 63 FR 37502, July 13, 1998]