Sec. 238.21  Special approval procedure.

    (a) General. The following procedures govern consideration and 
action upon requests for special approval of alternative standards under 
Secs. 238.103, 238.223, 238.309, 238.311, 238.405, or 238.427; for 
approval of alternative compliance under Sec. 238.201; and for special 
approval of pre-revenue service acceptance testing plans as required by 
Sec. 238.111. (Requests for approval of programs for the inspection, 
testing, and maintenance of Tier II passenger equipment are governed by 
Sec. 238.505.)
    (b) Petitions for special approval of alternative standard. Each 
petition for special approval of an alternative standard shall contain--
    (1) The name, title, address, and telephone number of the primary 
person to be contacted with regard to review of the petition;
    (2) The alternative proposed, in detail, to be substituted for the 
particular requirements of this part;
    (3) Appropriate data or analysis, or both, establishing that the 
alternative will provide at least an equivalent level of safety; and

[[Page 552]]

    (4) A statement affirming that the railroad has served a copy of the 
petition on designated representatives of its employees, together with a 
list of the names and addresses of the persons served.
    (c) Petitions for special approval of alternative compliance. Each 
petition for special approval of alternative compliance shall contain--
    (1) The name, title, address, and telephone number of the primary 
person to be contacted with regard to the petition;
    (2) The elements prescribed in Sec. 238.201(b); and
    (3) A statement affirming that the railroad has served a copy of the 
petition on designated representatives of its employees, together with a 
list of the names and addresses of the persons served.
    (d) Petitions for special approval of pre-revenue service acceptance 
testing plan.
    (1) Each petition for special approval of a pre-revenue service 
acceptance testing plan shall contain--
    (i) The name, title, address, and telephone number of the primary 
person to be contacted with regard to review of the petition; and
    (ii) The elements prescribed in Sec. 238.111.
    (2) Three copies of each petition for special approval of the pre-
revenue service acceptance testing plan shall be submitted to the 
Associate Administrator for Safety, Federal Railroad Administration, 
1120 Vermont Ave., N.W., Mail Stop 25, Washington, D.C. 20590.
    (e) Federal Register notice. FRA will publish a notice in the 
Federal Register concerning each petition under paragraphs (b) and (c) 
of this section.
    (f) Comment. Not later than 30 days from the date of publication of 
the notice in the Federal Register concerning a petition under 
paragraphs (b) and (c) of this section, any person may comment on the 
petition.
    (1) Each comment shall set forth specifically the basis upon which 
it is made, and contain a concise statement of the interest of the 
commenter in the proceeding.
    (2) Each comment shall be submitted to the DOT Central Docket 
Management System, Nassif Building, Room Pl-401, 400 Seventh Street, 
S.W., Washington, D.C. 20590, and shall contain the assigned docket 
number for that proceeding. The form of such submission may be in 
written or electronic form consistent with the standards and 
requirements established by the Central Docket Management System and 
posted on its web site at http://dms.dot.gov.
    (g) Disposition of petitions.
    (1) FRA will conduct a hearing on a petition in accordance with the 
procedures provided in Sec. 211.25 of this chapter.
    (2) If FRA finds that the petition complies with the requirements of 
this section or that the proposed plan is acceptable or changes are 
justified, or both, the petition will be granted, normally within 90 
days of its receipt. If the petition is neither granted nor denied 
within 90 days, the petition remains pending for decision. FRA may 
attach special conditions to the approval of the petition. Following the 
approval of a petition, FRA may reopen consideration of the petition for 
cause stated.
    (3) If FRA finds that the petition does not comply with the 
requirements of this section, or that the proposed plan is not 
acceptable or that the proposed changes are not justified, or both, the 
petition will be denied, normally within 90 days of its receipt.
    (4) When FRA grants or denies a petition, or reopens consideration 
of the petition, written notice is sent to the petitioner and other 
interested parties.