[Code of Federal Regulations]
[Title 49, Volume 6]
[Revised as of October 1, 2003]
From the U.S. Government Printing Office via GPO Access
[CITE: 49CFR611.13]

[Page 34-36]
 
                        TITLE 49--TRANSPORTATION
 
                             TRANSPORTATION
 
PART 611--MAJOR CAPITAL INVESTMENT PROJECTS--Table of Contents
 
Sec. 611.13  Overall project ratings.

    (a) The summary ratings developed for project justification local 
financial commitment (Sec. Sec. 611.9 and 611.11) will form the basis 
for the overall rating for each project.
    (b) FTA will assign overall ratings of ``highly recommended,'' 
``recommended,'' and ``not recommended,'' as required by 49 U.S.C. 
5309(e)(6), to each proposed project.
    (1) These ratings will indicate the overall merit of a proposed new 
starts project at the time of evaluation.
    (2) Ratings for individual projects will be updated annually for 
purposes of the annual report on funding levels and allocations of funds 
required by section 5309(o)(1), and as required for FTA approvals to 
enter into preliminary engineering, final design, or FFGAs.
    (c) These ratings will be used to:
    (1) approve advancement of a proposed project into preliminary 
engineering and final design;
    (2) Approve projects for FFGAs;
    (3) Support annual funding recommendations to Congress in the annual 
report on funding levels and allocations of funds required by 49 U.S.C. 
5309(o)(1); and
    (4) For purposes of the supplemental report on new starts, as 
required under section 5309(o)(2).
    (d) FTA will assign overall ratings for proposed new starts projects 
based on the following conditions:
    (1) Projects will be rated as ``recommended'' if they receive a 
summary rating of at least ``medium'' for both project justification 
(Sec. 611.9) and local financial commitment (Sec. 611.11);
    (2) Projects will be rated as ``highly recommended'' if they receive 
a summary rating higher than ``medium'' for both local financial 
commitment and project justification.
    (3) Projects will be rated as ``not recommended'' if they do not 
receive a summary rating of at least ``medium'' for both project 
justification and local financial commitment.

    Appendix A to Part 611--Description of Measures Used for Project 
                               Evaluation.

                          Project Justification

    FTA will use several measures to evaluate candidate new starts 
projects according to the criteria established by 49 U.S.C. 
5309(e)(1)(B). These measures have been developed according to the 
considerations identified at 49 U.S.C. 5309(e)(3) (``Project 
Justification''), consistent with Executive Order 12893. From time to 
time, FTA has published technical guidance on the application of these 
measures, and the agency expects it will continue to do so. Moreover, 
FTA may well choose to amend these measures, pending the results of 
ongoing studies regarding transit benefit evaluation methods. The first 
four criteria listed below assess the benefits of a proposed new start 
project by comparing the project to the baseline alternative. Therefore, 
the baseline alternative must be defined so that comparisons with the 
new start project isolate the costs and benefits of the major transit 
investment. At a minimum, the baseline alternative must include in the 
project corridor all reasonable cost-effective transit improvements 
short of investment in the new start project. Depending on the 
circumstances and through prior agreement with FTA, the baseline 
alternative can be defined appropriately in one of three ways. First, 
where the adopted financially constrained regional transportation plan 
includes within the corridor all reasonable cost-effective transit 
improvements short of the new start project, a no-build alternative that 
includes those improvements may serve as the baseline. Second, where 
additional cost-effective transit improvements can be made beyond those 
provided by the adopted plan, the baseline will add those cost-effective 
transit improvements. Third, where the proposed new start project is 
part of a multimodal alternative that includes major highway components, 
the baseline alternative will be the preferred multimodal alternative 
without the new start project and associated transit services. Prior to 
submittal of a request to enter preliminary engineering for the new 
start project, grantees must obtain FTA approval of the definition of 
the baseline alternative. Consistent with the requirement that 
differences between the new start project and the baseline alternative 
measure only the benefits and costs of the project itself, planning 
factors external to the new start project and its supporting bus service 
must be the same for both the baseline and new start project 
alternatives. Consequently, the highway and transit networks defined for 
the analysis must be the same outside the corridor for which the new 
start project is proposed. Further, policies affecting travel demand and 
travel costs,

[[Page 35]]

such as land use, transit fares and parking costs, must be applied 
consistently to both the baseline alternative and the new start project 
alternative. The fifth criterion, ``existing land use, transit 
supportive land use policies, and future patterns,'' reflects the 
importance of transit-supportive local land use and related conditions 
and policies as an indicator of ultimate project success.
    (a) Mobility Improvements.
    (1) The aggregate travel time savings in the forecast year 
anticipated from the new start project compared to the baseline 
alternative. This measure sums the travel time savings accruing to 
travelers projected to use transit in the baseline alternative, 
travelers projected to shift to transit because of the new start 
project, and non-transit users in the new start project who would 
benefit from reduced traffic congestion.
    (i) After September 1, 2001, FTA will employ a revised measure of 
travel benefits accruing to travelers.
    (ii) The revised measure will be based on a multi-modal measure of 
perceived travel times faced by all users of the transportation system.
    (2) The absolute number of existing low income households located 
within \1/2\-mile of boarding points associated with the proposed system 
increment.
    (3) The absolute number of existing jobs within \1/2\-mile of 
boarding points associated with the proposed system increment.
    (b) Environmental Benefits.
    (1) The forecast change in criteria pollutant emissions and in 
greenhouse gas emissions, ascribable to the proposed new investment, 
calculated in terms of annual tons for each criteria pollutant or gas 
(forecast year), compared to the baseline alternative;
    (2) The forecast net change per year (forecast year) in the regional 
consumption of energy, ascribable to the proposed new investment, 
expressed in British Thermal Units (BTU), compared to the baseline 
alternative; and
    (3) Current Environmental Protection Agency designations for the 
region's compliance with National Ambient Air Quality Standards.
    (c) Operating Efficiencies. The forecast change in operating cost 
per passenger-mile (forecast year), for the entire transit system. The 
new start will be compared to the baseline alternative.
    (d) Transportation System User Benefits (Cost-Effectiveness).
    (1) The cost effectiveness of a proposed project shall be evaluated 
according to a measure of transportation system user benefits, based on 
a multimodal measure of perceived travel times faced by all users of the 
transportation system, for the forecast year, divided by the incremental 
cost of the proposed project. Incremental costs and benefits will be 
calculated as the differences between the proposed new start and the 
baseline alternative.
    (2) Until the effective date of the transportation system user 
benefits measure of cost effectiveness, cost effectiveness will be 
computed as the incremental costs of the proposed project divided by its 
incremental transit ridership, as compared to the baseline alternative.
    (i) Costs include the forecast annualized capital and annual 
operating costs of the entire transit system.
    (ii) Ridership includes forecast total annual ridership on the 
entire transit system, excluding transfers.
    (e) Existing land use, transit supportive land use policies, and 
future patterns. Existing land use, transit-supportive land use 
policies, and future patterns shall be rated by evaluating existing 
conditions in the corridor and the degree to which local land use 
policies are likely to foster transit supportive land use, measured in 
terms of the kinds of policies in place, and the commitment to these 
policies. The following factors will form the basis for this evaluation:
    (1) Existing land use;
    (2) Impact of proposed new starts project on land use;
    (3) Growth-management policies;
    (4) Transit-supportive corridor policies;
    (5) Supportive zoning regulations near transit stations;
    (6) Tools to implement land use policies;
    (7) The performance of land use policies; and
    (8) Existing and planned pedestrian facilities, including access for 
persons with disabilities.
    (f) Other factors. Other factors that will be considered when 
evaluating projects for funding commitments include, but are not limited 
to:
    (1) Multimodal emphasis of the locally preferred investment 
strategy, including the proposed new start as one element;
    (2) Environmental justice considerations and equity issues,
    (3) Opportunities for increased access to employment for low income 
persons, and Welfare-to-Work initiatives;
    (4) Livable Communities initiatives and local economic activities;
    (5) Consideration of alternative land use development scenarios in 
local evaluation and decision making for the locally preferred transit 
investment decision;
    (6) Consideration of innovative financing, procurement, and 
construction techniques, including design-build turnkey applications; 
and
    (7) Additional factors relevant to local and national priorities and 
to the success of the project, such as Empowerment Zones, Brownfields, 
and FTA's Bus Rapid Transit Demonstration Program.

[[Page 36]]

                       Local Financial Commitment

    FTA will use the following measures to evaluate the local financial 
commitment to a proposed project:
    (a) The proposed share of project capital costs to be met using 
funds from sources other than the 49 U.S.C. 5309 new starts program, 
including both the local match required by Federal law and any 
additional capital funding (``overmatch''). Consideration will be given 
to:
    (i) The use of innovative financing techniques, as described in the 
May 9, 1995, Federal Register notice on FTA's Innovative Financing 
Initiative (60 FR 24682);
    (ii) The use of ``flexible funds'' as provided under the CMAQ and 
STP programs;
    (iii) The degree to which alternatives analysis and preliminary 
engineering activities were carried out without funding from the Sec. 
5309 new starts program; and
    (iv) The actual percentage of the cost of recently-completed or 
simultaneously undertaken fixed guideway systems and extensions that are 
related to the proposed project under review, from sources other than 
the section 5309 new starts program (FTA's intent is to recognize that a 
region's local financial commitment to fixed guideway systems and 
extensions may not be limited to a single project).
    (b) The stability and reliability of the proposed capital financing 
plan, according to:
    (i) The stability, reliability, and level of commitment of each 
proposed source of local match, including inter-governmental grants, tax 
sources, and debt obligations, with an emphasis on availability within 
the project development timetable;
    (ii) Whether adequate provisions have been made to cover 
unanticipated cost overruns and funding shortfalls; and
    (iii) Whether adequate provisions have been made to fund the capital 
needs of the entire transit system as planned, including key station 
plans as required under 49 CFR 37.47 and 37.51, over a 20-year planning 
horizon period.
    (c) The stability and reliability of the proposed operating 
financing plan to fund operation of the entire transit system as planned 
over a 20-year planning horizon.