Sec. 633.25  Contents of a project management plan.

    At a minimum, a recipient's project management plan shall include--
    (a) A description of adequate recipient staff organization, complete 
with well-defined reporting relationships, statements of functional 
responsibilities, job descriptions, and job qualifications;
    (b) A budget covering the project management organization, 
appropriate consultants, property acquisition, utility relocation, 
systems demonstration staff, audits, and such miscellaneous costs as the 
recipient may be prepared to justify;
    (c) A construction schedule;

[[Page 53]]

    (d) A document control procedure and recordkeeping system;
    (e) A change order procedure which includes a documented, systematic 
approach to the handling of construction change orders;
    (f) A description of organizational structures, management skills, 
and staffing levels required throughout the construction phase;
    (g) Quality control and quality assurance programs which define 
functions, procedures, and responsibilities for construction and for 
system installation and integration of system components;
    (h) Material testing policies and procedures;
    (i) Plan for internal reporting requirements including cost and 
schedule control procedures; and
    (j) Criteria and procedures to be used for testing the operational 
system or its major components;