[Code of Federal Regulations]
[Title 18, Volume 1]
[Revised as of April 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 18CFR11.11]
[Page 181-182]
TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES
CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
PART 11_ANNUAL CHARGES UNDER PART I OF THE FEDERAL POWER ACT--Table of Contents
Subpart B_Charges for Headwater Benefits
Sec. 11.11 Energy gains method of determining headwater benefits charges.
(a) Applicability. This section applies to any determination of
headwater benefits charges, unless:
(1) The Commission has approved headwater benefits charges pursuant
to an existing coordination agreement among the parties;
(2) The parties reach, and the Commission approves, a settlement
with respect to headwater benefits charges, pursuant to Sec. 11.14(a)
of this subpart; or
(3) Charges may be assessed under Sec. 11.14(b).
(b) General rule--(1) Summary. Except as provided in paragraph
(b)(3) of this section, a headwater benefits charge for a downstream
project is determined under this subpart by apportioning the section
10(f) costs of the headwater project among the headwater project and all
downstream projects that are not exempt from or waived from headwater
benefits charges under Sec. 11.10(b) of this chapter, according to each
project's share of the total energy benefits to those projects resulting
from the headwater project.
(2) Calculation; headwater benefits formula. The annual headwater
benefits charge for a downstream project is derived by multiplying the
section 10(f) cost by the ratio of the energy gains received by the
downstream project to
[[Page 182]]
the sum of total energy gains received by all downstream projects
(except those projects specified in Sec. 11.10(b) of this chapter) plus
the energy generated at the headwater project that is assigned to the
joint-use power cost, as follows:
[GRAPHIC] [TIFF OMITTED] TC14NO91.093
In which:
P=annual payment to be made for headwater benefits received by a
downstream project,
Cp=annual section 10(f) cost of the headwater project,
En=annual energy gains received at a downstream project, or
group of projects if owned by one entity,
Ed=annual energy gains received at all downstream projects
(except those specified in Sec. 11.10(b) of this chapter), and
Ej=portion of the annual energy generated at the headwater
project assigned to the joint-use power cost.
(3) If power generation is not a function of the headwater project,
section 10(f) costs will be apportioned only among the downstream
projects.
(4) If the headwater project is constructed after the downstream
project, liability for headwater benefits charges will accrue beginning
on the day on which any energy losses at the downstream project due to
filling the headwater reservoir have been offset by subsequent energy
gains. If the headwater project is constructed prior to the downstream
project, liability for headwater benefits charges will accrue beginning
on the day on which benefits are first realized by the downstream
project.
(5) No final charge assessed by the Commission under this subpart
may exceed 85 percent of the value of the energy gains. If a party
demonstrates, within the time specified in Sec. 11.17(b)(3) for
response to a preliminary assessment, that any final charge assessed
under this subpart, not including the cost of the investigation assessed
under Sec. 11.17(c), exceeds 85 percent of the value of the energy
gains provided to the downstream project for the period for which the
charge is assessed, the Commission will reduce the charge to not more
than 85 percent of the value. For purposes of this paragraph, the value
of the energy gains is the cost of obtaining an equivalent amount of
electricity from the most likely alternative source during the period
for which the charge is assessed.