[Code of Federal Regulations] [Title 18, Volume 1] [Revised as of April 1, 2004] From the U.S. Government Printing Office via GPO Access [CITE: 18CFR12.30] [Page 198] TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY PART 12_SAFETY OF WATER POWER PROJECTS AND PROJECT WORKS--Table of Contents Subpart D_Inspection by Independent Consultant Sec. 12.30 Applicability. This subpart applies to any licensed project development that has a dam: (a) That is more than 32.8 feet (10 meters) in height above streambed, as defined in Sec. 12.31(c); (b) That impounds an impoundment with a gross storage capacity of more than 2,000 acre-feet (2.5 million cubic meters); or (c) That has a high hazard potential and is determined by the Regional Engineer or other authorized Commission representative to require inspection by an independent consultant under this subpart.