Sec. 12.36  Emergency corrective measures.

    If, in the course of an inspection, an independent consultant 
discovers any condition for which emergency corrective measures are 
advisable, the independent consultant must immediately notify the 
licensee and the licensee must report that condition to the Regional 
Engineer pursuant to Sec. 12.10(a) of this part.