Sec. 153.23  Reporting requirements.

    Each person authorized under this part 153 that is not otherwise 
required to file information concerning the start of construction or 
modification of import/export facilities, the completion of construction 
or modification, and the commencement of service must file such 
information with the Commission within 10 days after such event. Each 
person, other than entities without pipeline capacity, must also report 
by March 1 of each year the estimated peak day capacity and actual peak 
day usage of its import/export facilities.