[Code of Federal Regulations]
[Title 18, Volume 1]
[Revised as of April 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 18CFR154.204]

[Page 479]
 
           TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES
 
  CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
 
PART 154_RATE SCHEDULES AND TARIFFS--Table of Contents
 
                Subpart C_Procedures for Changing Tariffs
 
Sec. 154.204  Changes in rate schedules, forms of service agreements, or the general terms and conditions.

    A filing to revise rate schedules, forms of service agreements, or 
the general terms and conditions, must:
    (a) Adhere to the requirements of subparts A, B, and C, of this 
part;
    (b) Contain a description of the change in service, including, but 
not limited to, applicability, necessity for the change, identification 
of services and types of customers that will be affected by the change;
    (c) Explain how the proposed tariff provisions differ from those 
currently in effect, including an example showing how the existing and 
proposed tariff provisions operate. Explain why the change is being 
proposed at this time;
    (d) Explain the impact of the proposed revision on firm and 
interruptible customers, including any changes in a customer's rights to 
capacity in the manner in which a customer is able to use such capacity, 
receipt or delivery point flexibility, nominating and scheduling, 
curtailment, capacity release;
    (e) Include workpapers showing the estimated effect on revenues and 
costs over the 12-month period commencing on the proposed effective date 
of the filing. If the filing proposes to change an existing penalty 
provision, provide workpapers showing the penalty revenues and 
associated quantities under the existing penalty provision during the 
latest 12-month period; and
    (f) List other filings pending before the Commission which may 
significantly affect the filing.