[Code of Federal Regulations]
[Title 18, Volume 1]
[Revised as of April 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 18CFR154.206]

[Page 479-480]
 
           TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES
 
  CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
 
PART 154_RATE SCHEDULES AND TARIFFS--Table of Contents
 
                Subpart C_Procedures for Changing Tariffs
 
Sec. 154.206  Motion to place suspended rates into effect.

    (a) If, prior to the end of the suspension period, the Commission 
has issued an order requiring changes in the filed rates, or the filed 
rates recover costs for facilities not certificated and in service as of 
the proposed effective date, in order to place the suspended rates into 
effect, the pipelne must file a motion at least one day prior to the 
effective date requested by the pipeline. The motion must be accompanied 
by revised tariff sheets reflecting any changes ordered by the 
Commission or modifications approved by the Commission during the 
suspension period under Sec. 154.205. The filing of the revised tariff 
sheets must:
    (1) Comply with the requirements of subparts A, B, and C of this 
part;
    (2) Identify the Commission order directing the revision;
    (3) List the modifications made to the currently effective rate 
during the

[[Page 480]]

suspension period, the docket number in which the modifications were 
filed, and identify the order permitting the modifications.
    (b) Where the Commission has suspended the effective date of a 
change of rate, charge, classification, or service for a minimal period 
and the pipeline has not included a motion in its transmittal letter, or 
has specified in its transmittal letter pursuant to Sec. 154.7(a)(9), 
that it reserves its right to file motion to place the proposed change 
of rate, charge, classification, or service into effect at the end of 
the suspension period, the change will go into effect, subject to 
refund, upon motion of the pipeline.
    (c) Where the Commission has suspended the effective date of a 
change of rate, charge, classification, or service for a minimal period 
and the pipeline has included, in its transmittal letter pursuant to 
Sec. 154.7(a)(9), a motion to place the proposed change of rate, 
charge, classification, or service into effect at the end of the 
suspension period, the change will go into effect, subject to refund, on 
the authorized effective date.