Sec. 154.309  Incremental expansions.

    (a) For every expansion for which incremental rates are charged, the 
company must provide a summary with applicable cross-references to Sec. 
154.312 and Sec. 154.313, of the costs and revenues associated with the 
expansion, until the Commission authorizes the costs of the incremental 
facilities to be rolled-in to the pipeline's rates. For every expansion 
that has an at-risk provision in the certificate authorization, the 
costs and revenues associated with the facility must be shown in summary 
format with applicable cross-references to Sec. 154.312 and Sec. 
154.313, until the Commission removes the at-risk condition.
    (b) The summary statements must provide the formulae and explain the 
bases used in the allocation of common costs to each incremental 
facility.