[Code of Federal Regulations]
[Title 18, Volume 1]
[Revised as of April 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 18CFR16.22]

[Page 224]
 
           TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES
 
  CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
 
PART 16_PROCEDURES RELATING TO TAKEOVER AND RELICENSING OF LICENSED 
PROJECTS--Table of Contents
 
  Subpart E_Projects With Minor and Minor Part Licenses Not Subject to 
               Sections 14 and 15 of the Federal Power Act
 
Sec. 16.22  Application for an exemption by a licensee with a minor or 

minor part license for a project not subject to sections 14 and 15 of 
the Federal Power Act.

    (a) Applicability. This section applies to an existing licensee with 
a license for a project not subject to sections 14 and 15 of the Federal 
Power Act.
    (b) Information requirements. An applicant for an exemption must 
meet the requirements of, and will be processed in accordance with, 
subpart K or subpart J of part 4 of this chapter, and Sec. Sec. 16.5, 
16.8, 16.9(b)(2) (except the requirement to comply with Sec. Sec. 4.41, 
4.51, or 4.61 of this chapter), Sec. Sec. 16.9(b)(3), 16.9(b)(4), 
16.9(c), 16.9(d), and 16.20(c).
    (c) Standard of comparison. If an application for subsequent license 
is filed in competition with an application for exemption by an existing 
licensee, the Commission will decide among competing applications in 
accordance with the standards of Sec. 16.13 and not in accordance with 
the provisions of Sec. 4.37(d)(2) of this chapter.