[Code of Federal Regulations]
[Title 18, Volume 1]
[Revised as of April 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 18CFR2.104]

[Page 35-37]
 
           TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES
 
  CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
 
PART 2_GENERAL POLICY AND INTERPRETATIONS--Table of Contents
 
Sec. 2.104  Mechanisms for passthrough of pipeline take-or-pay buyout 
and buydown costs.

    (a) General Policy. The Commission as a matter of policy will 
provide two distinct mechanisms for passthrough of take-or-pay buyout 
and buydown costs of interstate natural gas pipelines. The first is 
pursuant to existing Commission policy and practice. Under this method, 
pipelines may pass through prudently incurred take-or-pay buyout and 
buydown costs in their sales commodity rates. The second method is 
available to pipelines which agree to an equitable sharing of take-or-
pay costs and which transport under part 284 of this chapter. Qualifying 
pipelines may utilize the alternative passthrough mechanisms described 
in this section. Where a pipeline agrees to absorb from 25 to 50 percent 
of take-or-pay buyout and buydown costs, the Commission will permit the 
pipeline to recover through a fixed charge an amount equal to (but not 
greater than) the amount absorbed. Any remaining costs up to 50 percent 
of total buyout and buydown costs may be recovered either through a 
commodity rate surcharge or a volumetric surcharge on total throughput.
    (b) Cost allocation procedures. A pipeline's volume-based surcharges 
must be based on the volumes which underlie its most recent Commission-
approved rates. Fixed charges must be based on each customer's 
cumulative deficiency in purchases in recent years (during which the 
current take-or-pay liabilities of the pipelines were incurred) measured 
in relation to that customer's purchases during a representative period 
during which take-or-pay liabilities were not incurred. The allocation 
formula employed must incorporate the following guidelines:
    (1) A representative base period must be selected. The base period 
must reflect a representative level of purchases by the pipeline's firm 
customers during a period preceding the onset of changed conditions 
which resulted in reduced purchases and growth of the take-or-pay 
problem.
    (2) Firm purchases by each customer during the base year under firm 
rate schedules or contracts for firm service must be determined.

[[Page 36]]

    (3) Firm sales purchase deficiency volumes for each subsequent year 
must be determined.
    (4) A fixed charge based on each customer's cumulative deficiencies 
as compared to total cumulative deficiencies must be derived. The filing 
pipeline will be free to select for rate calculation and filing purposes 
a reasonable amortization period for buyout and buydown costs being 
recovered through fixed charges or volumetric surcharges. The pipeline 
will be entitled to interest at the rate set forth in part 154 of this 
chapter on unamortized amounts.
    (c) Implementing procedures. (1) Pipelines acting pursuant to this 
section may submit on or before December 31, 1990, a non-PGA rate filing 
under section 4(e) of the Natural Gas Act. Pipelines may include in 
their filings a fixed charge and a volumetric surcharge to recover 
buyout and buydown costs actually paid as of the date of filing plus 
similar costs which are known and measurable within the following nine 
months. Detailed support for the amounts claimed and for the calculation 
of customer surcharges must be provided. In addition, the pipeline must 
disclose and describe all consideration, both cash and noncash, given to 
producers in exchange for take-or-pay relief.
    (2) In any filings made under this section, pipelines must include 
proposals for periodic (preferably annual) adjustments to customer 
surcharges, together with any necessary accounting procedures, designed 
to assure that revenues recovered by the pipeline remain in balance with 
buyout and buydown costs covered by the filing and actually incurred by 
the pipeline.
    (d) Prudence. (1) The Commission will examine the issue of prudence 
if it is raised by a party in an individual proceeding. If it is raised, 
the pipeline will be required to demonstrate the prudence of take-or-pay 
buyout and buydown costs which it seeks to recover from its customers 
through both fixed and volume-based charges.
    (2) The Commission intends to exercise its authority to the full 
extent permitted by the Natural Gas Act to approve take-or-pay 
settlements. The Commission intends to approve uncontested take-or-pay 
settlements which are consistent with this section and found to be in 
the public interest. The Commission will also, if it appears reasonable 
and permissible to do so, approve contested settlements as to all 
consenting parties and initiate separate hearings to establish the rates 
for opposing parties. Alternatively, the Commission will approve 
contested settlements on the merits if supported by substantial evidence 
in the record. In any case where hearings are held as to the prudence of 
take-or-pay buyout and buydown costs, the Commission will permit the 
pipeline the opportunity to recover all take-or-pay costs found to be 
prudent from the contesting parties on a proportional basis, even if the 
amount allowed is greater than the amounts initially sought to be 
recovered by the pipeline.
    (e) Flowthrough by downstream pipelines. Downstream pipelines must 
flow through approved take-or-pay fixed charges based on the cumulative 
purchase deficiencies of their customers. Volumetrically-based 
surcharges must be flowed through on a volumetric basis. Customers of 
downstream pipelines have the right in connection with either PGA or 
general rate filings to challenge the purchasing practices of such 
pipelines. Remedies for purchasing practices found by the Commission to 
be imprudent will be determined on a case-by-case basis.
    (f) Ongoing proceedings. Pipeline rate proceedings pending September 
15, 1987 may be utilized as a forum for implementing the approved cost 
recovery mechanisms set forth in this section. Permission will be 
granted in cases where implementation of this policy in pending 
proceedings appears feasible, will not result in inordinate delay, or 
can be expected to result in unnecessary or cumulative rate filings with 
the Commission. In the event permission is granted, the presiding 
judge(s) will allow pipelines to supplement their filings to the extent 
necessary to assure compliance with the filing and data requirements set 
forth herein. The presiding judges shall also establish any procedures 
necessary to protect the rights of all parties. Any rates established 
pursuant to this section will be permitted to become effective only

[[Page 37]]

prospectively upon Commission approval.
    (g) Scope. This section does not go beyond the Commission's 
determination in the April 10, 1985, policy statement (Docket No. PL85-
1-000) that take-or-pay buyout and buydown costs do not violate the 
pricing provision of the Natural Gas Policy Act of 1978 (NGPA). It is 
not intended to affect take-or-pay prepayments made by pipelines and 
included in account 165 and in their rate bases. Nor does it address the 
issue of whether take-or-pay prepayments to a producer for gas not taken 
and which cannot be made up violate the Title I pricing provisions of 
the NGPA. This policy statement applies only to buyout and buydown costs 
paid by pipelines that are transporting under part 284 of this chapter, 
under existing contracts, and is not intended to disturb in any way 
take-or-pay settlements previously entered into between pipelines and 
their producer suppliers.

[Order 500, 52 FR 30351, Aug. 14, 1987, as amended at 52 FR 35539, Sept. 
22, 1987; Order 500-F, 53 FR 50924, Dec. 19, 1988; 54 FR 52394, Dec. 21, 
1989; Order 581, 60 FR 53064, Oct. 11, 1995]