           TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES
 
  CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
 
PART 270_DETERMINATION PROCEDURES--Table of Contents
 
           Subpart B_Determinations by Jurisdictional Agencies
 
Sec. 270.204  Notice to the Commission.

    Within 15 days after making a determination under this part, the 
jurisdictional agency must give written notice of the determination to 
the Commission. The notice must include the following:
    (a) A list of all participants in the proceeding as well as any 
persons who submitted or who sought an opportunity to submit written 
comments (whether or not such persons participated in the proceeding);
    (b) A statement indicating whether the matter was opposed before the 
jurisdictional agency;
    (c) A copy of the application together with a copy or description of 
all other materials upon which the jurisdictional agency relied in the 
course of making the determination, together with any information which 
may be inconsistent with the determination.
    (d) An explanatory statement, including appropriate factual findings 
and references, which is sufficient to enable a person examining the 
notice to ascertain the basis for the determination without reference to 
information or data not contained in the notice.