[Code of Federal Regulations]
[Title 18, Volume 1]
[Revised as of April 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 18CFR286.101]

[Page 759]
 
           TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES
 
  CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
 
PART 286_ADMINISTRATIVE PROCEDURES--Table of Contents
 
Sec. 286.101  Application for stay.




Sec.
286.101 Application for stay.
286.102 Application for rehearing.

    Authority: Administrative Procedure Act, 5 U.S.C. 551 et seq., 
Natural Gas Policy Act of 1978, Pub. L. 95-621, 92 Stat. 3350, 
Department of Energy Organization Act, Pub. L. 95-91, E.O. 12009, 42 FR 
46267.


    (a) General rule. Any person who believes that any provision of a 
final or interim regulation issued under the Natural Gas Policy Act of 
1978 is unlawful as applied to such person may file an application for 
stay.
    (b) Content of application. The application shall state, clearly and 
concisely:
    (1) The provision of the regulation, by section, paragraph, 
subparagraph and clause, as appropriate, which applicant seeks to have 
stayed;
    (2) The conditions which the applicant believes require the stay, 
including the irreparable injury which the applicant believes will 
result if the stay is not granted; and
    (3) The factual and legal basis for applicant's contention that the 
final or interim regulation is unlawful.
    (c) Filing requirements. The application shall be under oath. An 
original and three conformed copies shall be filed with the Secretary of 
the Commission.
    (d) Commission action. The Commission may grant the application, in 
whole or in part, by issuing an order specifying the scope of the stay 
granted and the effective dates of the stay.

[43 FR 57599, Dec. 8, 1978, as amended at 44 FR 13473, Mar. 12, 1979]