           TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES
 
  CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
 
PART 32_INTERCONNECTION OF FACILITIES--Table of Contents
 
Sec. 32.2  Required exhibits.

    There shall be filed with the application and as a part thereof the 
following exhibits:

    Exhibit A. Statement of the estimated capital cost of all facilities 
required to establish the connection, and the estimated annual cost of 
operating such facilities.
    Exhibit B. A general or key map on a scale not greater than 20 miles 
to the inch showing, in separate colors, the territory served by each 
utility, and the location of the facilities used for the generation and 
transmission of electric energy, indicating on said map the points 
between which connection may be established most economically.