[Code of Federal Regulations]
[Title 18, Volume 1]
[Revised as of April 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 18CFR4.12]

[Page 70]
 
           TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES
 
  CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
 
PART 4_LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF PROJECT 
COSTS--Table of Contents
 
  Subpart B_Determination of Fair Value of Constructed Projects, Under 
                        Section 23(a) of the Act
 
Sec. 4.12  Service of report.

    A copy of such report will be served by certified mail upon said 
licensee, and copies will also be sent to the State public service 
commission, or if the State has no regulatory agency, to the Governor of 
the State where such project is located. The report will be made 
available for public inspection at the time of service upon the 
licensee.

(Administrative Procedure Act, 5 U.S.C. 551-557 (1976); Federal Power 
Act, as amended, 16 U.S.C. 291-628 (1976 & Supp. V 1981), Dept. of 
Energy Organization Act 42 U.S.C. 7101-7352 (Supp. V 1981); E.O. 12009, 
3 CFR 142 (1978))

[Order 141, 12 FR 8485, Dec. 19, 1947, as amended by Order 344, 48 FR 
49010, Oct. 24, 1983]