[Code of Federal Regulations] [Title 18, Volume 1] [Revised as of April 1, 2004] From the U.S. Government Printing Office via GPO Access [CITE: 18CFR4.22] [Page 71] TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY PART 4_LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF PROJECT COSTS--Table of Contents Subpart C_Determination of Cost of Constructed Projects not Subject to Section 23(a) of the Act Sec. 4.22 Service of report. Copies of such report will be served by certified mail upon said licensees, and copies will also be sent to the State public service commission, or if the State has no regulatory agency, to the Governor of the State where such project is located, and to such other parties as the Commission shall prescribe, and the report will be made available for public inspection at the time of service upon the licensee. (Administrative Procedure Act, 5 U.S.C. 551-557 (1976); Federal Power Act, as amended, 16 U.S.C. 291-628 (1976 & Supp. V 1981), Dept. of Energy Organization Act 42 U.S.C. 7101-7352 (Supp. V 1981); E.O. 12009, 3 CFR 142 (1978)) [Order 141, 12 FR 8485, Dec. 19, 1947, as amended by Order 344, 48 FR 49010, Oct. 24, 1983]