           TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES
 
  CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
 
PART 4_LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF PROJECT 
COSTS--Table of Contents
 
 Subpart C_Determination of Cost of Constructed Projects not Subject to 
                        Section 23(a) of the Act
 
Sec. 4.24  Determination of cost.

    The Commission, after receipt of the reports, or after the 
conclusion of the hearing if one is held, will determine the amounts to 
be included in the electric plant accounts of the licensee as the cost 
of the property and the accrued depreciation thereon.