[Code of Federal Regulations]
[Title 18, Volume 1]
[Revised as of April 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 18CFR4.25]

[Page 72]
 
           TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES
 
  CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
 
PART 4_LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF PROJECT 
COSTS--Table of Contents
 
 Subpart C_Determination of Cost of Constructed Projects not Subject to 
                        Section 23(a) of the Act
 
Sec. 4.25  Findings.

    (a) Commission determination. Final action by the Commission will be 
in the form of an order served upon all parties to the proceeding. One 
copy of the order shall be furnished to the Secretary of Treasury by the 
Commission.
    (b) Adjustment to licensee's books. The licensee's books of account 
for the project shall be adjusted to conform to the actual legitimate 
cost as revised by the order of the Commission. These adjustments and 
the project may be audited by Commission representatives, as scheduled.

[Order 53, 44 FR 61949, Oct. 29, 1979]