[Code of Federal Regulations]
[Title 18, Volume 1]
[Revised as of April 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 18CFR4.6]

[Page 70]
 
           TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES
 
  CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
 
PART 4_LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF PROJECT 
COSTS--Table of Contents
 
  Subpart A_Determination of Cost of Projects Constructed Under License
 
Sec. 4.6  Burden of proof.

    The burden of proof to sustain each item of claimed cost shall be 
upon the licensee and only such items as are in the opinion of the 
Commission supported by satisfactory proof may be entered in the 
electric plant accounts of the licensee.

[Order 53, 44 FR 61948, Oct. 29, 1979]