[Code of Federal Regulations]
[Title 18, Volume 1]
[Revised as of April 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 18CFR4.7]

[Page 70]
 
           TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES
 
  CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
 
PART 4_LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF PROJECT 
COSTS--Table of Contents
 
  Subpart A_Determination of Cost of Projects Constructed Under License
 
Sec. 4.7  Findings.

    (a) Commission determination. Final action by the Commission will be 
in the form of an order served upon all parties to the proceeding. One 
copy of the order will be furnished to the Secretary of Treasury by the 
Commission.
    (b) Adjustments to licensee's books. The licensee's books of account 
for the project shall be adjusted to conform to the actual legitimate 
cost as revised by the order of the Commission. These adjustments and 
the project may be audited by Commission representatives, as scheduled.

[Order 53, 44 FR 61948, Oct. 29, 1979]