[Code of Federal Regulations]
[Title 18, Volume 1]
[Revised as of April 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 18CFR4.81]

[Page 122-124]
 
           TITLE 18--CONSERVATION OF POWER AND WATER RESOURCES
 
  CHAPTER I--FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
 
PART 4_LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF PROJECT 
COSTS--Table of Contents
 
Subpart I_Application for Preliminary Permit; Amendment and Cancellation 
                          of Preliminary Permit
 
Sec. 4.81  Contents of application.

    Each application for a preliminary permit must include the following 
initial statement and numbered exhibits containing the information and 
documents specified:
    (a) Initial statement:

             Before the Federal Energy Regulatory Commission

                   Application for Preliminary Permit

    (1) [Name of applicant] applies to the Federal Energy Regulatory 
Commission for a preliminary permit for the proposed [name of project] 
water power project, as described in the attached exhibits. This 
application is made in order that the applicant may secure and maintain 
priority of application for a license for the project under Part I of 
the Federal Power Act while obtaining the data and performing the acts 
required to determine the feasibility of the project and to support an 
application for a license.
    (2) The location of the proposed project is:

State or territory:_____________________________________________________
County:_________________________________________________________________
Township or nearby town:________________________________________________
Stream or other body of water:__________________________________________
________________________________________________________________________
    (3) The exact name, business address, and telephone number of the 
applicant are:

________________________________________________________________________
________________________________________________________________________
________________________________________________________________________

    The exact name and business address of each person authorized to act 
as agent for the applicant in this application are:
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
    (4) [Name of applicant] is a [citizen, association, citizens, 
domestic corporation, municipality, or State, as appropriate] and (is/is 
not) claiming preference under section 7(a) of the Federal Power Act. 
[If the applicant is a municipality, the applicant must submit copies of 
applicable state or local laws or a municipal charter or, if such laws 
or documents are not clear, any other appropriate legal authority, 
evidencing that the municipality is competent under such laws to engage 
in the business of development, transmitting, utilizing, or distributing 
power].
    (5) The proposed term of the requested permit is [period not to 
exceed 36 months].
    (6) If there is any existing dam or other project facility, the 
applicant must provide the name and address of the owner of the dam and 
facility. If the dam is federally owned or operated, provide the name of 
the agency.

    (b) Exhibit 1 must contain a description of the proposed project, 
specifying and including, to the extent possible:
    (1) The number, physical composition, dimensions, general 
configuration and, where applicable, age and condition, of any dams, 
spillways, penstocks, powerhouses, tailraces, or other structures, 
whether existing or proposed, that would be part of the project;
    (2) The estimated number, surface area, storage capacity, and normal 
maximum surface elevation (mean sea level) of any reservoirs, whether 
existing or proposed, that would be part of the project;
    (3) The estimated number, length, voltage, interconnections, and, 
where applicable, age and condition, of any primary transmission lines 
whether existing or proposed, that would be part of the project [see 16 
U.S.C. 796(11)];
    (4) The total estimated average annual energy production and 
installed capacity (provide only one energy and capacity value), the 
hydraulic head for estimating capacity and energy output, and the 
estimated number, rated capacity, and, where applicable, the age and 
condition, of any turbines and generators, whether existing or proposed, 
that would be part of the project works;
    (5) All lands of the United States that are enclosed within the 
proposed project boundary described under paragraph (e)(3) of this 
section, identified and tabulated on a separate sheet by legal 
subdivisions of a public land survey of the affected area, if available. 
If the project boundary includes lands of the United States, such lands 
must be identified on a completed land description form, provided by the 
Commission. The project location must identify any Federal reservation, 
Federal tracts, and townships of the public land surveys (or official 
protractions thereof if unsurveyed). A copy of the form must also be 
sent to the Bureau of Land

[[Page 123]]

Management state office where the project is located;
    (6) Any other information demonstrating in what manner the proposed 
project would develop, conserve, and utilize in the public interest the 
water resources of the region.
    (c) Exhibit 2 is a description of studies conducted or to be 
conducted with respect to the proposed project, including field studies. 
Exhibit 2 must supply the following information:
    (1) General requirement. For any proposed project, a study plan 
containing a description of:
    (i) Any studies, investigations, tests, or surveys that are proposed 
to be carried out, and any that have already taken place, for the 
purposes of determining the technical, economic, and financial 
feasibility of the proposed project, taking into consideration its 
environmental impacts, and of preparing an application for a license for 
the project; and
    (ii) The approximate locations and nature of any new roads that 
would be built for the purpose of conducting the studies; and
    (2) Work plan for new dam construction. For any development within 
the project that would entail new dam construction, a work plan and 
schedule containing:
    (i) A description, including the approximate location, of any field 
study, test, or other activity that may alter or disturb lands or waters 
in the vicinity of the proposed project, including floodplains and 
wetlands; measures that would be taken to minimize any such disturbance; 
and measures that would be taken to restore the altered or disturbed 
areas; and
    (ii) A proposed schedule (a chart or graph may be used), the total 
duration of which does not exceed the proposed term of the permit, 
showing the intervals at which the studies, investigations, tests, and 
surveys, identified under this paragraph are proposed to be completed.
    (iii) For purposes of this paragraph, new dam construction means any 
dam construction the studies for which would require test pits, borings, 
or other foundation exploration in the field.
    (3) Waiver. The Commission may waive the requirements of paragraph 
(c)(2) pursuant to Sec. 385.207 of this chapter, upon a showing by the 
applicant that the field studies, tests, and other activities to be 
conducted under the permit would not adversely affect cultural resources 
or endangered species and would cause only minor alterations or 
disturbances of lands and waters, and that any land altered or disturbed 
would be adequately restored.
    (d) Exhibit 3 must contain a statement of costs and financing, 
specifying and including, to the extent possible:
    (1) The estimated costs of carrying out or preparing the studies, 
investigations, tests, surveys, maps, plans or specifications identified 
under paragraph (c) of this section;
    (2) The expected sources and extent of financing available to the 
applicant to carry out or prepare the studies, investigations, tests, 
surveys, maps, plans, or specifications identified under paragraph (c) 
of this section; and
    (3) A description of the proposed market for the power generated at 
the project, including:
    (i) The identity of the proposed purchaser(s) of the power, and any 
information that is available concerning the revenues to be derived from 
the sale of the power; or
    (ii) If the applicant proposes to utilize the power output, the size 
of the applicant's power system, system peak demand and annual energy 
requirements, and the number of customers served by the applicant.
    (e) Exhibit 4 must include a map or series of maps, to be prepared 
on United States Geological Survey topographic quadrangle sheets or 
similar topographic maps of a State agency, if available. The maps need 
not conform to the precise specifications of Sec. 4.39 (a) and (b). If 
the scale of any base map is not sufficient to show clearly and legibly 
all of the information required by this paragraph, the maps submitted 
must be enlarged to a scale that is adequate for that purpose. (If 
Exhibit 4 comprises a series of maps, it must also include an index 
sheet showing, by outline, the parts of the entire project covered by 
each map of the series.) The maps must show:

[[Page 124]]

    (1) The location of the project as a whole with reference to the 
affected stream or other body of water and, if possible, to a nearby 
town or any permanent monuments or objects that can be noted on the maps 
and recognized in the field;
    (2) The relative locations and physical interrelationships of the 
principal project features identified under paragraph (b) of this 
section;
    (3) A proposed boundary for the project, enclosing:
    (i) All principal project features identified under paragraph (b) of 
this section, including but not limited to any dam, reservoir, water 
conveyance facilities, powerplant, transmission lines, and other 
appurtenances; if the project is located at an existing Federal dam, the 
Federal dam and impoundment must be shown, but may not be included 
within the project boundary;
    (ii) Any non-Federal lands and any public lands or reservations of 
the United States [see 16 U.S.C. 796 (1) and (2)] necessary for the 
purposes of the project. To the extent that those public lands or 
reservations are covered by a public land survey, the project boundary 
must enclose each of and only the smallest legal subdivisions (quarter-
quarter section, lots, or other subdivisions, identified on the map by 
subdivision) that may be occupied in whole or in part by the project.
    (4) Areas within or in the vicinity of the proposed project boundary 
which are included in or have been designated for study for inclusion in 
the National Wild and Scenic Rivers System; and
    (5) Areas within the project boundary that, under the provisions of 
the Wilderness Act, have been:
    (i) Designated as wilderness area;
    (ii) Recommended for designation as wilderness area; or
    (iii) Designated as wilderness study area.

(Federal Power Act, as amended, 16 U.S.C. 792-828c (1976); Department of 
Energy Organization Act, 42 U.S.C. 7101-7352 (Supp. IV 1980); E.O. 
12009, 3 CFR part 142 (1978); 5 U.S.C. 553 (Supp. IV 1980))

[Order 54, 44 FR 61336, Oct. 25, 1979, as amended by Order 123, 46 FR 
9029, Jan. 28, 1981; 46 FR 11811, Feb. 11, 1981; Order 225, 47 FR 19056, 
May 3, 1982; Order 413, 50 FR 11685, Mar. 25, 1985; Order 2002, 68 FR 
51120, Aug. 25, 2003]