Sec. 630.402  Policy.

    (a) Geodetic surveys along Federal-aid highway routes may be 
programmed as Federal-aid highway projects.
    (b) All geodetic survey work performed as a Federal-aid highway 
project will conform to National Ocean Survey (NOS) specifications. NOS 
will, as the representative of FHWA, be responsible for the inspection 
and verification of the work to ascertain that the specifications for 
the work have been met. Final project acceptance by FHWA will be 
predicated on a finding of acceptability by NOS.